What happened Sungrow (300274.SZ) announced that the EDC Kandal Stueng (GS79) energy storage station in Cambodia — rated at 108.4 MW/215.6 MWh — has reached full-capacity grid connection. The project uses Sungrow's PowerTitan grid-forming energy storage system. According to the company, the project passed a full set of system-level, all-dimension grid-connection tests in a single attempt. These included large-scale black start, extended islanded supply, and multiple rounds of grid-connected/islanded mode switching. Sungrow positions the result as a new benchmark for the scaled, standardized deployment of grid-forming storage technology in Southeast Asia's complex grid environments. The black start was used to energize a large islanded network combining storage, thermal generation, hydro generation and load. Traditional grids rely heavily on synchronous machines — thermal and hydro units — to provide voltage and frequency support, and lack a self-starting voltage source when the whole area loses power, making restoration slow and difficult. Sungrow says PowerTitan broke through this limitation by establishing voltage from zero without relying on conventional main generating units, giving the project system-level black-start self-healing capability. A total of 516 grid-forming PCS units coordinated to build voltage, balancing output across parallel machines and suppressing circulating current. The system withstood five main-transformer excitation surges of up to 100 MVA each, and successfully formed a large islanded network of storage, thermal, hydro and load for extended islanded supply. With the storage system independently establishing voltage and frequency, 240 km of 220 kV lines and five substations were rapidly restored, improving local supply continuity and reliability. The site's grid is highly dynamic and switching between operating conditions is frequent, placing strict demands on steady-state control precision and stability. The project completed three rounds of high-difficulty seamless grid-connected/islanded switching, described as smooth and controllable throughout, with no oscillation and no disconnection. Sungrow attributes this to its grid-forming control algorithms and multi-condition coordinated control strategy. For delivery, Sungrow provided a grid-tailored grid-forming solution. Its project team worked closely with technical experts from Cambodia's national grid operator, pooling multidisciplinary resources to build a high-precision grid simulation platform that replicated on-site network parameters and grid operating characteristics at 1:1 scale. Sungrow said it will continue to supply integrated storage solutions for Southeast Asia's new power system build-out and regional green energy transition. ### Key figures - Project capacity: 108.4 MW/215.6 MWh - Location: Kandal Stueng (GS79), Cambodia; owner/offtaker context: EDC (Electricité du Cambodge) - Grid-forming PCS units coordinated: 516 - Main-transformer excitation surges withstood: 5, each up to 100 MVA - Grid-connected/islanded seamless switching tests completed: 3 rounds - Grid restored: 240 km of 220 kV lines and 5 substations - Simulation platform fidelity: 1:1 replication of site network parameters - Announcement date: 2026-09-30 ### Why it matters to ebm-papst This is a reference win for grid-forming storage in a difficult Southeast Asian grid, and it signals accelerating deployment of large BESS assets in the region. For ebm-papst, the direct relevance is cooling: high-capacity storage stations and their PCS/transformer containers require reliable, energy-efficient thermal management, and Sungrow's standardized PowerTitan platform implies repeatable, volume-oriented component demand rather than one-off engineering. Assessment (inference): ebm-papst is not a direct competitor to Sungrow in storage inverters or grid-forming controls, so the near-term risk is competitive displacement only where fan and blower content is specified by other suppliers on Sungrow platforms. The larger opportunity is as a qualified cooling supplier for containerized BESS and PCS skids, where high ambient temperatures, dust, and continuous duty in Cambodia and neighboring markets favor robust, low-maintenance fan solutions. Assessment (inference): the emphasis on standardized, scalable grid-forming deployment suggests procurement will increasingly be platform-based, so early engagement with Sungrow's PowerTitan supply chain and with EPCs active in Cambodia, Vietnam and Thailand would be more valuable than project-by-project bidding. Assessment (inference): the black-start and islanded-supply capability also points to growing demand for backup and off-grid power quality, adjacent segments where ebm-papst cooling and air-moving products are already specified.

Full text

Original English translation
Hardcore clearance! Sungrow completes full-dimension verification of large-scale black start in Southeast Asia Recently, the EDC Kandal Stueng (GS79) 108.4 MW/215.6 MWh energy storage station in Cambodia achieved full-capacity grid connection. The project is equipped with Sungrow's PowerTitan grid-forming energy storage system. Large-scale black start, long-duration islanded supply, and multiple rounds of grid-connected/islanded switching — system-level, all-dimension grid-connection tests — passed in a single attempt, setting another new benchmark for the scaled and standardized deployment of grid-forming energy storage technology in Southeast Asia's complex grid scenarios. Black start drives a large islanded network of storage, thermal, hydro and load Traditional power grids rely heavily on synchronous units such as thermal and hydro generation to provide voltage and frequency support. When the entire area loses power, there is no self-starting voltage source, the restoration process is cumbersome, and recovery is difficult. Sungrow's PowerTitan grid-forming energy storage system breaks through the limitations of traditional grid operation. Without relying on conventional main generating units, it achieves zero-start autonomous voltage establishment from a passive grid, giving the project system-level black-start self-healing capability. 516 grid-forming PCS units coordinate to establish voltage, with balanced output across parallel machines and suppression of circulating current. They withstand five main-transformer excitation surges of up to 100 MVA each, successfully building a large islanded network of storage, thermal, hydro and load with strong surge resistance and stable control, achieving long-duration islanded supply. Through the energy storage system independently establishing voltage and frequency, 240 km of local 220 kV lines and five substations were rapidly restored, greatly improving the continuity and reliability of local grid power supply. Extreme adaptation to complex grid conditions, three rounds of seamless grid-connected/islanded switching The grid where the project is located has prominent dynamic fluctuation characteristics and frequent switching of operating conditions, placing strict demands on equipment steady-state control precision and operational stability, and making grid dynamic disturbances highly likely. Facing different operating conditions, the project successfully completed three rounds of high-difficulty seamless grid-connected/islanded switching tests, with the entire switching process smooth and controllable, with no oscillation and no disconnection. Relying on mature grid-forming control algorithms and multi-condition coordinated control strategies, the system precisely adapts to the grid's dynamic fluctuation characteristics, effectively safeguarding steady-state safe operation of the grid under frequent condition switching. To ensure high-quality project delivery, Sungrow provided a grid-tailored grid-forming solution. The project team cooperated deeply with technical experts from Cambodia's national grid, assembling multidisciplinary professional resources to build a high-precision grid simulation platform, replicating on-site network parameters and grid operating characteristics at 1:1 scale, enabling high-quality project implementation and operation. In the future, Sungrow will continue to provide highly reliable, high-performance integrated energy storage solutions for the construction of Southeast Asia's new power system and the region's green energy transition.