# Sungrow, Trina Storage and two peers land 2.3GWh of overseas storage orders across Germany, Australia, CEE

- Source: News · Sungrow (T2)
- Published: 2026-09-21
- Score: 68.4
- Tags: Order win, ESS, Datacenter
- Companies: Sungrow (300274.SZ)
- Original: https://www.seetao.com/details/278953.html

## Intelligence brief

### What happened On 20 September 2026, TrendForce EnergyTrend, together with overseas energy media, reported that four Chinese energy-storage companies — Sungrow (300274.SZ), Trina Storage, Weili New Energy and Naton Energy — had recently closed a cluster of overseas storage orders totalling more than 2.3GWh, spanning Germany, Australia, Hungary and other core overseas storage markets. Sungrow signed a two-year framework agreement with German storage developer be.storaged, targeting 1.6GWh. be.storaged is the storage development platform of German energy group EWE and focuses on local project development, grid permits and long-term operations. Under the agreement, Sungrow supplies its full PowerTitan 3.0 liquid-cooled storage system and technical solution, while the partner handles early-stage development, civil works, grid-connection approval and long-term O&M. The two sides plan to standardise on this system across multiple German standalone storage plants to shorten construction cycles and cut the landed cost of GWh-scale projects. In Australia, Trina Storage won the phase-one storage order for the Waroona renewable energy project in Western Australia: 81.5MW / 562MWh, paired with a 132MW PV plant. The site lies about 120km south of Perth, with roughly 6.9 hours of storage duration and commissioning expected in 2028. The project uses Trina's Elementa DC-coupled storage solution, enabling coordinated PV-plus-storage control suited to the weak-grid conditions of Western Australia's long-distance network. The contract includes 20-year warranty and O&M services. Two smaller deals also closed: Weili New Energy agreed a 150MWh framework with Hungarian energy company Szermann Kft to deliver multiple C&I storage projects in Hungary and neighbouring Central and Eastern European countries over the coming year; and Naton Energy shipped 5MWh of commercial and industrial storage equipment to the European market. ### Key figures - Combined order volume of the four companies: more than 2.3GWh - Sungrow–be.storaged framework: 1.6GWh, two-year term - Trina Storage Waroona phase one: 81.5MW / 562MWh, with a 132MW PV plant - Waroona storage duration: approximately 6.9 hours; commissioning expected 2028 - Waroona site: about 120km south of Perth, Western Australia - Waroona warranty and O&M term: 20 years - Weili New Energy–Szermann Kft framework: 150MWh over the next year - Naton Energy shipment: 5MWh of C&I storage equipment - Report date: 20 September 2026 ### Why it matters to ebm-papst This is a demand-side signal rather than a direct competitive threat: liquid-cooled, GWh-scale battery storage and DC-coupled PV-plus-storage plants require large volumes of fans and blowers for thermal management of battery containers, inverters and power conversion equipment. Sungrow's PowerTitan 3.0 platform and Trina's Elementa solution are exactly the kind of standardised, repeat-build architectures that lock in component suppliers early, so qualification with these OEMs and their container integrators matters more than ever. The German framework is the most strategically relevant item. Germany's strict grid, safety and temperature-control standards, combined with EWE-backed long-term operation, mean any cooling component specified into these plants will be held to high reliability and service-life requirements — a fit for ebm-papst's premium positioning, but also a barrier if we are not already on the approved vendor list. Assessment (inference): The shift described in the report — from selling equipment to full-lifecycle system solutions plus long-term O&M — implies that fan suppliers will increasingly be evaluated on serviceability, spare-part availability and local technical support in Europe and Australia, not just unit price. Assessment (inference): The 20-year warranty on the Waroona project suggests multi-decade aftermarket and retrofit revenue potential for cooling components, which favours suppliers with established local service footprints. Assessment (inference): The CEE C&I segment targeted by Weili and Naton is lower volume per project but higher in project count, and may be better served through distribution partners than direct OEM design-ins. Assessment (inference): ebm-papst should prioritise design-in engagement with Sungrow and Trina Storage container platforms, and monitor whether European utilities and developers begin specifying fan-level reliability or efficiency requirements in storage tenders.

## Full text (English translation)

On 20 September 2026, TrendForce EnergyTrend, together with overseas energy media, disclosed in a concentrated manner that four Chinese energy-storage companies — Sungrow, Trina Storage, Weili New Energy and Naton Energy — had recently closed overseas storage orders in a concentrated wave, with a combined total scale exceeding 2.3GWh, covering core overseas storage markets including Germany, Australia and Hungary. The news quickly drew widespread industry attention. This group of orders landing in a concentrated period demonstrates the comprehensive competitiveness of domestic storage system manufacturers in the European and Australian markets, and also reflects that storage going overseas is shifting from simply selling equipment to competition based on full-lifecycle system solutions plus long-term O&M services.

Sungrow locks in a major German order
Sungrow signed a two-year framework agreement for storage projects with German local storage developer be.storaged, with a target cooperation scale of 1.6GWh. be.storaged is the storage development platform under German energy giant EWE, deeply engaged in local storage project development, grid permits and long-term operations. Under the agreement, Sungrow will provide the complete PowerTitan 3.0 liquid-cooled storage system product and technical solution, while the partner is responsible for early-stage project development, civil works, grid-connection approval and later long-term O&M. The two sides plan to uniformly adopt this standardised storage system across multiple standalone storage plant projects in Germany, shortening project construction cycles and reducing the landed cost of GWh-scale storage projects. Germany has strong grid peak-shaving demand and stringent standards for storage system safety, temperature control and reliability; the landing of this framework represents large-scale recognition by a German local developer of a domestic large-scale liquid-cooled storage system solution.

Trina Storage deepens its work in Australia
In the Australian market, Trina Storage won the phase-one storage order for the Waroona renewable energy project in Western Australia, with a scale of 81.5MW/562MWh, paired with a 132MW PV plant. The project site is about 120km south of Perth, with a storage duration of about 6.9 hours, and is expected to be commissioned in 2028. The project adopts Trina's Elementa DC-coupled storage solution, which can achieve coordinated control of PV and storage and adapt to the weak-grid operating characteristics of Western Australia's long-distance grid. This order agreement includes 20-year warranty and O&M services, a clause that overseas owners increasingly value. Western Australia's grid spans enormous distances and is rich in wind and solar resources but lacks grid stability; long-duration storage is a key support for local renewable energy consumption, which is an important reason Trina Storage continues to deepen its presence in Australia's integrated wind-solar-storage track. Keywords: New Energy News Network, energy storage, companies going overseas

Flexible landing in Central and Eastern European niche markets
In addition, two small and medium-sized orders landed simultaneously. Weili New Energy reached a 150MWh storage framework cooperation with Hungarian energy company Szermann Kft, planning to land multiple commercial and industrial storage projects in Hungary and neighbouring Central and Eastern European countries over the next year. Naton Energy completed shipment of 5MWh of commercial and industrial storage equipment, with products sold to the European market. From the order distribution it is not hard to see that domestic storage manufacturers going overseas have already formed a differentiated layout logic: Sungrow focuses on large-scale standalone grid storage in Europe, Trina Storage focuses on integrated wind-solar-storage projects in Australia, and small and medium-sized storage companies target the commercial and industrial storage niche markets of Central and Eastern Europe. The competitive logic of overseas markets has undergone a fundamental change: grid compliance capability, system safety performance, localised delivery and long-cycle O&M guarantees have become hard thresholds for overseas owners when screening suppliers. (This article comes from the Seetao official website www.seetao.com; reproduction without permission is prohibited; please indicate Seetao + the original link when reprinting.) Seetao New Energy column editor/Gao Xue

Comments
Write something...

## Full text (original)

2026年9月20日，集邦EnergyTrend联合海外能源媒体集中披露，阳光电源、天合储能、伟力新能源、纳通能源四家中国储能企业近期集中落地海外储能订单，合计总规模突破2.3GWh，项目覆盖德国、澳大利亚、匈牙利等核心海外储能市场。消息一出迅速引发行业广泛关注，这组集中落地的订单，集中展现国内储能系统厂商在欧洲、澳洲市场的综合竞争力，也折射出储能出海正在从单纯卖设备，转向全周期系统方案加长期运维服务的竞争新阶段。
阳光电源锁定德国大单
阳光电源与德国本土储能开发商be.storaged签署为期两年的储能项目框架协议，合作目标规模1.6GWh。be.storaged是德国能源巨头EWE旗下储能开发平台，深耕本土储能项目开发、电网许可与长期运营。协议约定，阳光电源将提供PowerTitan 3.0液冷储能系统全套产品与技术方案，合作方负责项目前期开发、土建、并网审批以及后期长期运维。双方计划在德国多个独立储能电站项目统一采用这套标准化储能系统，缩短项目建设周期，降低GWh级储能项目的落地成本。德国电网调峰需求旺盛，对储能系统安全、温控、可靠性标准严苛，本次框架落地代表国产大型液冷储能系统方案获得德国本土开发商的大规模认可。
天合储能深耕澳洲
澳洲市场方面，天合储能拿下西澳Waroona可再生能源项目一期储能订单，规模81.5兆瓦562兆瓦时，配套132兆瓦光伏电站。项目选址在珀斯以南约120公里，储能时长约6.9小时，预计2028年投产。项目选用天合Elementa直流耦合储能方案，能够实现光伏与储能的协同管控，适配西澳远距离电网的弱网运行特性。本次订单协议包含长达20年质保与运维服务，也是海外业主越来越看重的条款。西澳电网跨度巨大，风光资源丰富但电网稳定性不足，长时储能是当地新能源消纳的关键支撑，这也是天合储能持续深耕澳洲风光储一体化赛道的重要原因。关键词：新能源新闻网、储能、企业出海
中东欧细分市场灵活落地
除此之外，还有两笔中小体量订单同步落地。伟力新能源与匈牙利能源企业Szermann Kft达成150兆瓦时储能框架合作，计划未来一年在匈牙利及周边中东欧国家落地多个工商业储能项目。纳通能源5兆瓦时工商业储能设备完成发运，产品销往欧洲市场。从订单分布不难看出，国内储能厂商出海已经形成差异化布局逻辑，阳光电源主攻欧洲大型独立电网储能，天合储能聚焦澳洲风光储一体化项目，中小型储能企业则瞄准中东欧工商业储能细分市场。海外市场的竞争逻辑已经发生根本性变化，电网合规能力、系统安全性能、本地化交付、长周期运维保障，已经成为海外业主筛选供应商的硬性门槛。（此文出自见道官网www.seetao.com未经允许不得转载否则必究，转载请注明见道网+原文链接）见道网新能源栏目编辑/高雪