### What happened On 17 September 2026, the tenderer for the Weichang Deyu grid-side independent energy storage demonstration project published the shortlist of winning candidates for the procurement of a 297MW/1188MWh lithium iron phosphate (LFP) battery energy storage system (BESS). The project is located at the buyer-designated site in Weichang Manchu and Mongol Autonomous County, Chengde City, Hebei Province, China. The three shortlisted candidates, in ranked order, are: 1. Tianjin Ruiyuan Electric Co., Ltd. — bid RMB 619,542,000, equivalent to RMB 0.5215/Wh 2. Sungrow Power Supply Co., Ltd. — bid RMB 607,129,500, equivalent to RMB 0.5111/Wh 3. Shenzhen Clou Electronics Co., Ltd. — bid RMB 617,760,000, equivalent to RMB 0.52/Wh According to the simultaneously disclosed bid-opening record, nine companies submitted bids: Clou Electronics, Ruiyuan Electric, Sungrow, Envision Energy, Trina Storage, Zhiguang Energy Storage, Diangong Shidai (Shandong Electrical Engineering & Equipment Group Energy Technology), Tiancheng Tongchuang, and hyperstrong. The overall bid range was RMB 0.511–0.535/Wh. The announcement states that six bidders — Envision Energy Co., Ltd., Jiangsu Trina Storage Co., Ltd., Guangzhou Zhiguang Energy Storage Technology Co., Ltd., Shandong Diangong Shidai Energy Technology Co., Ltd., Beijing Tiancheng Tongchuang Electric Co., Ltd., and Beijing hyperstrong Technology Co., Ltd. — had their bids rejected because their sealed (anonymous) bid documents did not meet the requirements of the tender documents. Project scope: the Weichang Deyu grid-side independent energy storage demonstration project is planned as a 300MW/1200MWh storage system, built in a single phase. The configuration comprises 297MW/1188MWh of high-performance LFP battery storage plus 3MW/12MWh of all-vanadium flow battery storage, together with a new 220kV storage power station. The tender covers the 297MW/1188MWh LFP BESS equipment, including all equipment, spare parts, special tools and ancillary equipment required for normal operation, plus supervised installation. It excludes the 35kV cables between the 35kV switchgear inside the booster station and the storage system step-up transformer, and between the storage system step-up transformers. Delivery: supply is scheduled to start on 30 September 2026 and to be completed by 30 November 2026. The source notes that this is a candidate-stage announcement only and does not represent the final award; the final result is subject to the tenderer's official announcement. ### Key figures - Tender size: 297MW/1188MWh LFP BESS (part of a planned 300MW/1200MWh project) - Additional scope: 3MW/12MWh all-vanadium flow battery storage; one new 220kV storage power station - First candidate (Tianjin Ruiyuan Electric): RMB 619,542,000; RMB 0.5215/Wh - Second candidate (Sungrow): RMB 607,129,500; RMB 0.5111/Wh - Third candidate (Clou Electronics): RMB 617,760,000; RMB 0.52/Wh - Number of bidders: 9 submitted; 6 rejected on sealed-bid documentation grounds - Overall bid range: RMB 0.511–0.535/Wh - Delivery start: 30 September 2026; delivery completion: 30 November 2026 - Location: Weichang Manchu and Mongol Autonomous County, Chengde City, Hebei Province, China - Announcement date: 17 September 2026 ### Why it matters to ebm-papst This tender is a large grid-side BESS deployment in Hebei, and the pricing outcome is a market signal for the cost pressure across China's storage supply chain. Sungrow, a major ebm-papst-relevant account in the inverter and energy storage segment, placed second with the lowest bid of the three shortlisted candidates (RMB 0.5111/Wh) yet was not ranked first, indicating that price alone did not determine ranking in this evaluation. Assessment (inference): For ebm-papst, the most direct relevance is cooling. Containerized LFP BESS at this scale (297MW/1188MWh, plus a 3MW/12MWh flow-battery portion) requires large volumes of fans and blowers for thermal management of battery containers, power conversion systems and the associated 220kV station. If Sungrow or another shortlisted supplier is ultimately awarded, it represents a potential component demand opportunity, though ebm-papst's access depends on whether the winning system integrator designs in ebm-papst cooling or sources locally. Assessment (inference): The rejection of six bidders, including hyperstrong and Trina Storage, on documentation grounds rather than technical or commercial grounds suggests the competitive field was narrowed administratively; this reduces the number of system integrators that can influence component selection for this specific project, concentrating the opportunity among the three shortlisted firms. Assessment (inference): The bid range of RMB 0.511–0.535/Wh confirms continued aggressive price competition in Chinese grid-side storage. Sustained low system prices tend to push integrators toward cost-optimized cooling architectures, which can pressure fan content value per MWh even as total storage volumes grow — a structural signal worth tracking for ebm-papst's China energy-storage business. Assessment (inference): The 30 September 2026 supply start and 30 November 2026 completion imply a very short delivery window, so component sourcing decisions for the winning bidder are likely already underway or imminent; engagement should be treated as time-sensitive. Note that this is a candidate-stage announcement and the final award is not confirmed.

## Full text (English translation)

Source: Public disclosure materials on the winning candidates for the Weichang Deyu grid-side independent energy storage demonstration project.

On 17 September, the winning candidates for the procurement of the 297MW/1188MWh lithium iron phosphate battery energy storage system equipment for the Weichang Deyu grid-side independent energy storage demonstration project were publicly announced. The specific information is as follows:

First winning candidate: Tianjin Ruiyuan Electric Co., Ltd.
Bid price: RMB 619,542,000
Equivalent unit price: RMB 0.5215/Wh

Second winning candidate: Sungrow Power Supply Co., Ltd.
Bid price: RMB 607,129,500
Equivalent unit price: RMB 0.5111/Wh

Third winning candidate: Shenzhen Clou Electronics Co., Ltd.
Bid price: RMB 617,760,000
Equivalent unit price: RMB 0.52/Wh

According to the simultaneously disclosed bid-opening record, a total of nine companies submitted bid documents, namely Clou Electronics, Ruiyuan Electric, Sungrow, Envision Energy, Trina Storage, Zhiguang Energy Storage, Diangong Shidai, Tiancheng Tongchuang, and hyperstrong; the overall bid range was RMB 0.511–0.535/Wh.

The announcement shows that a total of six entities — Envision Energy Co., Ltd., Jiangsu Trina Storage Co., Ltd., Guangzhou Zhiguang Energy Storage Technology Co., Ltd., Shandong Diangong Shidai Energy Technology Co., Ltd., Beijing Tiancheng Tongchuang Electric Co., Ltd., and Beijing hyperstrong Technology Co., Ltd. — had their bid documents rejected because their sealed-bid preparation did not meet the relevant requirements of the tender documents.

Project overview
The Weichang Deyu grid-side independent energy storage demonstration project is planned to build a 300MW/1200MWh energy storage system, to be completed in a single phase. The storage configuration includes 297MW/1188MWh of high-performance lithium iron phosphate battery storage as well as 3MW/12MWh of all-vanadium flow battery storage; the project is accompanied by a newly built 220kV energy storage power station.

Scope of tender
This tender procurement covers the 297MW/1188MWh lithium iron phosphate battery energy storage system equipment, including the supply of all equipment, spare parts, special tools and ancillary equipment necessary for the normal operation of the project, as well as supervised installation. It excludes the 35kV cables between the 35kV switchgear inside the booster station and the energy storage system step-up transformer, and between the energy storage system step-up transformers.

Delivery location: the buyer-designated location at the project site in Weichang Manchu and Mongol Autonomous County, Chengde City, Hebei Province.

Delivery period: equipment supply is planned to start on 30 September 2026 and to be completed by 30 November 2026.

The original text is as follows:

(Note: This article is compiled from the public announcement of the project's winning candidates. This announcement is only candidate-stage information and does not represent the final winning result; the final project result is subject to the tenderer's official announcement. This article is not to be used as a basis for equipment procurement, project, or stock investment decisions.)

4001102288 Feedback and corrections welcome
All Rights Reserved Sina Company Copyright

## Full text (original)

来源：围场德御电网侧独立储能综合示范项目中标候选人公开公示资料
9月17日，围场德御电网侧独立储能综合示范项目297MW/1188MWh磷酸铁锂电池储能系统设备采购中标候选人对外公示。具体信息如下：
第一中标候选人：天津瑞源电气有限公司
投标报价：619542000元
折合单价：0.5215元/Wh
第二中标候选人：阳光电源股份有限公司
投标报价：607129500元
折合单价：0.5111元/Wh
第三中标候选人：深圳市科陆电子科技股份有限公司
投标报价：617760000元
折合单价：0.52元/Wh
根据同步公开的开标记录，本次共有9家企业递交投标文件，分别为科陆电子、瑞源电气、阳光电源、远景能源、天合储能、智光储能、电工时代、天诚同创、海博思创；整体报价区间0.511~0.535元/Wh。
公告显示，远景能源有限公司、江苏天合储能有限公司、广州智光储能科技有限公司、山东电工时代能源科技有限公司、北京天诚同创电气有限公司、北京海博思创科技股份有限公司共6家单位，因暗标编制不满足招标文件相关要求，投标文件予以否决。
项目概况
围场德御电网侧独立储能综合示范项目规划建设300MW/1200MWh储能系统，本期一次性建成。储能配置包含297MW/1188MWh高性能磷酸铁锂电池储能以及3MW/12MWh全钒液流电池储能；项目配套新建一座220kV储能电站。
招标范围
本次招标采购为297MW/1188MWh磷酸铁锂电池储能系统设备，包含项目正常运行必需全部设备、备品备件、专用工具、附属设备供货以及指导安装。不含升压站内35kV开关柜至储能系统升压变压器、储能系统升压变压器之间的35kV线缆。
交货地点：河北省承德市围场满族蒙古族自治县项目现场买方指定地点。
交货期：计划设备2026年9月30日启动供货，2026年11月30日前完成全部供货。
原文如下：
（备注：本文整理自项目中标候选人公开公示。本公示仅为候选人阶段信息，不代表最终中标结果，项目最终结果以招标方正式公告为准。本文不作为设备采购、项目、股票投资决策依据。）