# Silan Jihua's 12-inch analog chip project in Xiamen targets full topping-out by end-2026

- Source: JW Insights (T2)
- Published: 2026-01-01
- Score: 0.0
- Tags: Cleanroom
- Original: https://www.laoyaoba.com/n/1102219

## Intelligence brief

### What happened Silan Jihua (a subsidiary of Silan Microelectronics) is advancing its 12-inch high-end analog integrated circuit project in Xiamen, Fujian Province. As of late 2025, the basement and foundation raft works have been fully completed, and construction teams for the upper main structures of the south plot's main fab and the north plot's power and ancillary facilities have entered the site. The project's chief commander, Zhu Lirong, disclosed key milestones: full structural topping-out is planned for end-December 2026, fab delivery for May 2027, and pilot production for September 2027. This schedule is ahead of the original plan, which targeted pilot production in Q4 2027. The project is a key provincial industrial initiative with a total investment of RMB 20 billion, adopting an IDM (Integrated Device Manufacturer) model. It will be implemented in two phases: Phase 1 will add 20,000 wafers per month, and Phase 2 will add another 25,000 wafers per month. Silan Microelectronics already operates multiple chip manufacturing bases in Haicang, Xiamen, and has attracted over 70 upstream and downstream semiconductor companies to form a regional cluster. Further updates on topping-out, equipment move-in, and production ramp-up are expected from the company and construction partners. ### Key figures - Total investment: RMB 20 billion - Phase 1 monthly capacity: 20,000 wafers - Phase 2 additional monthly capacity: 25,000 wafers - Full topping-out: end-December 2026 - Fab delivery: May 2027 - Pilot production: September 2027 (original plan: Q4 2027) - Number of supporting companies in the cluster: over 70 ### Why it matters to ebm-papst This project represents a significant expansion of semiconductor manufacturing capacity in China, which will drive demand for cleanroom facilities and associated HVAC systems. As a leading provider of fans and motors for cleanroom applications, ebm-papst could see increased opportunities for supplying high-efficiency, low-noise fans and motors to this and similar projects. The accelerated timeline suggests a sense of urgency in the semiconductor industry, potentially leading to faster procurement cycles. Assessment (inference): The project's scale and IDM model indicate a long-term commitment to analog chip production, which may create sustained demand for cleanroom infrastructure and replacement parts. ebm-papst should monitor such developments to align its product offerings and sales strategies with the specific needs of semiconductor fabs, such as energy efficiency and reliability. Additionally, the clustering of semiconductor companies in Xiamen could make it a regional hub for cleanroom technology demand, offering a strategic market for ebm-papst to strengthen its presence.

## Full text (English translation)

Recently, the construction of Xiamen Silan Jihua's 12-inch high-end analog integrated circuit project has made new progress. The basement and foundation raft works have been fully completed, and the construction units for the upper main structures of the south plot's main fab and the north plot's power and ancillary facilities have entered the site for construction.

Zhu Lirong, the general commander of the Xiamen Silan Engineering Headquarters, disclosed key construction milestones: the project is planned to achieve full structural topping-out by the end of December 2026, the fab is expected to be delivered in May 2027, and the target is to achieve pilot production (通线投产) in September 2027. Compared with the original plan of pilot production in Q4 2027, the overall construction progress has been accelerated.

The project is a key provincial industrial project in Fujian Province, with a total investment of RMB 20 billion. It will build a 12-inch high-end analog chip production line and operate under the IDM model. The project will be implemented in two phases: Phase 1 plans a monthly capacity of 20,000 wafers, and Phase 2 will add a monthly capacity of 25,000 wafers.

Silan Microelectronics has already laid out multiple chip manufacturing bases in Haicang, Xiamen. The local area has gathered more than 70 upstream and downstream semiconductor supporting enterprises around Silan, forming a regional semiconductor industry cluster. The actual progress of the Silan Jihua project's subsequent topping-out, equipment move-in, and production ramp-up still awaits further disclosure by the enterprise and construction parties.

(Proofread by Li Zhengcao)

## Full text (original)

近日，厦门士兰集华12英寸高端模拟集成电路项目建设取得新进展，项目地下室及基础筏板工程已经全部完工，南地块主厂房、北地块动力及配套设施的上部主体施工单位已进场开展施工。
厦门士兰工程指挥部总指挥朱利荣对外披露项目关键建设节点，项目计划2026年12月底实现全面封顶，厂房预计2027年5月完成交付，目标2027年9月实现通线投产。对比项目最初规划的2027年四季度通线，整体建设进度有所提前。
该项目为福建省重点产业项目，总投资200亿元，建设12英寸高端模拟芯片产线，采用IDM模式运营。项目分两期实施，一期规划月产能2万片，二期新增月产能2.5万片。
士兰微已在厦门海沧布局多处芯片制造基地，当地围绕士兰微集聚七十余家半导体上下游配套企业，形成区域性半导体产业集群。士兰集华项目后续封顶、设备搬入及投产实际进度，仍有待企业与建设方后续对外披露。
（校对/李正操）