### What happened Soitec, a French chip material maker, is signing multi-year supply agreements with customers as demand for wafers used in optical components for AI data centers surges. CEO Laurent Remont said the company is leveraging the current market situation to find the right balance between the value it provides and the prices it can charge. The company is collecting deposits and fixing prices in these contracts. Soitec expects about 80% of its capacity reservation agreements with photonics customers to be signed within one to two weeks, with the rest within a month. Cash deposits are not yet paid and will be received in stages as customers ramp up capacity. The contracts specify prices and require customers to pay deposits tied to committed demand. Customers meeting agreed volumes get deposits refunded; those failing lose deposits; those exceeding volumes trigger new price negotiations. Customers must also share inventory data to prevent over-ordering, which would leave wafers for competitors. Soitec expects no need for new factories until around 2029, relying on two expansion plans: using shared idle facilities to transfer capacity between business units, and adding equipment to existing cleanroom space. ### Key figures - Photonics-SOI revenue expected to more than double from just over $100 million this fiscal year, exceeding $200 million (CEO calls it "absolute floor"). - Soitec holds approximately 95% market share in substrates for silicon photonics (UBS estimate). - Stock price has nearly quadrupled this year. - About 80% of capacity reservation agreements expected to be signed within one to two weeks; rest within a month. - No new factories needed until around 2029. ### Why it matters to ebm-papst Soitec's expansion plans involve adding equipment to existing cleanroom spaces and transferring capacity between business units, which may require upgrades to cleanroom infrastructure, including air handling and filtration systems. This could present opportunities for ebm-papst to supply fans and motors for cleanroom ventilation and temperature control. Additionally, the surge in AI-driven demand for optical components signals a broader trend of increased semiconductor manufacturing, which could lead to more cleanroom projects globally. Assessment (inference): ebm-papst should monitor Soitec's capacity expansion and similar moves by other semiconductor material suppliers, as they may drive demand for high-efficiency, reliable fan systems in cleanroom environments.

## Full text (English translation)

French chip material maker Soitec's CEO said that due to surging demand for wafers required for optical components in AI data centers, the company is signing multi-year supply agreements with customers, collecting deposits, and fixing prices.

"We are leveraging the current situation to find the right balance between the value we provide and the prices we can charge," said Laurent Remont.

Last month, Soitec told investors that its photonics-SOI revenue for this fiscal year would more than double from just over $100 million. This means revenue will exceed $200 million, which Remont now calls an "absolute floor."

Demand for silicon photonics has surged as hyperscale data centers increasingly use optical connections to transmit data within AI infrastructure, while copper cable connections are becoming less attractive due to power consumption and performance limitations.

Soitec provides substrates for silicon photonic chips. UBS estimates the company holds a 95% market share. The company's stock has nearly quadrupled this year as AI-related optical network demand accelerates.

Remont said that about 80% of Soitec's capacity reservation agreements with photonics customers are expected to be signed within one to two weeks, with the rest expected within a month. Cash deposits have not yet been paid and will be received in stages as customers ramp up capacity.

The contracts specify prices and require customers to pay deposits tied to committed demand. Customers who meet agreed volumes will receive deposit refunds; those who fail to meet agreed volumes will lose deposits. Customers who exceed agreed volumes will trigger new price negotiations.

"This allows us to ensure customer interests are tied to the contract," Remont said.

He added that customers must also share inventory data, a requirement aimed at preventing companies from over-ordering capacity, thereby leaving wafers for competitors.

Remont said Soitec expects no need to build new factories until around 2029. The company is currently advancing two expansion plans: one is to use shared idle facilities to transfer capacity between business units; the other is to add equipment to existing cleanroom space.

"With these, we can easily cover capacity this year and next year," he said.

"We don't need to build new fabs; we can quickly increase capacity by retrofitting existing buildings," Remont said.

## Full text (original)

法国芯片材料制造商 Soitec 首席执行官表示，由于人工智能数据中心光学器件所需的晶圆需求激增，该公司正与客户签订多年供应协议，并收取定金，同时确定固定价格。
“我们正在利用当前形势，在我们所提供的价值和我们能够收取的价格之间找到合适的平衡点，”Laurent Remont 表示。
Soitec 上个月告诉投资者，本财年光子学-SOI 收入将从略高于 1 亿美元翻一番以上。这意味着收入将超过 2 亿美元，Remont 现在称之为“绝对的底线”。
由于超大规模数据中心越来越多地使用光连接在人工智能基础设施内部传输数据，而铜缆连接由于功耗和性能限制而吸引力下降，因此对硅光子学的需求激增。
Soitec 为硅光子芯片提供衬底。瑞银估计该公司占据了95%的市场份额。随着人工智能相关光网络需求的加速增长，该公司股价今年已上涨近四倍。
Remont表示，Soitec与光子学客户签订的产能预订协议中，约80%预计将在一两周内签署，其余协议预计将在一个月内签署。现金订金尚未支付，将随着客户产能的提升分阶段到账。
合同规定了价格，并要求客户支付与承诺需求挂钩的订金。达到约定产量的客户将获得订金退款；未达到约定产量的客户将损失订金。超过约定产量的客户将触发新的价格谈判。
“这让我们能够确保客户利益与合同挂钩，”Remont说道。
他还补充说，客户还必须共享库存数据，这项要求旨在防止企业过度订购产能，从而将晶圆留给竞争对手。
Remont表示，Soitec预计在2029年左右之前无需新建工厂。公司目前正在推进两项扩张计划：一是利用共享的闲置设施在不同业务部门间转移产能；二是为现有洁净室空间增设设备。
“有了这些，我们今年和明年的产能都能轻松覆盖，”他说道。