AIDC供电终极解法?800V落地仍存盲点,SST尚需验证
情报详报
What happened At the 2026 China Intelligent Computing Industry Ecosystem Development Conference, industry experts discussed the urgent power supply challenges facing AI data centers (AIDCs). Zhang Jiabin, a senior expert engineer at Tencent Data Center, highlighted that GPU parallel architectures cause severe power fluctuations, with entire clusters behaving like a single computer, leading to tens to hundreds of megawatts of power swings. The industry is converging on high-voltage DC (HVDC) solutions, particularly 800V DC, as a key architecture. However, experts noted that commercial HVDC still faces issues like low power density (around 150kW per cabinet), vendor variability, and operational complexity. Four main technical routes are being pursued: PowerRack/Sidecar, Panama Power (DCUPS), Integrated DC Power Pod, and Solid-State Transformer (SST). SST is seen as the 'ultimate form' but remains unproven. The conference also covered energy storage strategies, policy drivers, and the need for ecosystem-wide collaboration. ### Key figures - Single-rack power: from 10kW (traditional) to 140kW (AI computing), with next-gen AI servers planning 200kW-300kW. - GPU load spikes: from 155% (Volta) to 180% (Hopper) to over 200% (Blackwell GB300), with steady-state accuracy tightening from ±10% to ±5%. - Traditional AC UPS power distribution can occupy over 50% of cabinet space in high-density scenarios. - Commercial HVDC power density: only ~150kW per cabinet. - SST can improve efficiency by over 4% and save over 60% floor space compared to traditional solutions. - Zhiguang's Coota1.0 product: 10kV to 800V direct conversion, 98.5% efficiency, capacity range 1MW-4.2MW. - Energy storage: MW-level large storage for campus clusters, supercapacitors for power supply transients, and CBU/electrolytic capacitors for server-level millisecond fluctuations. - Diesel generators: 1800kW units struggle to meet frequency recovery standards when load changes exceed ~10%. - GPU room battery health: frequent charge/discharge may shorten lifespan from 5 years to less than 3 years. - Cascaded high-voltage direct-mounted storage: direct connection to 6-36kV grid, response ≤5ms, system efficiency 92%, 6-10 percentage points higher than traditional low-voltage storage. - Policy: national hub nodes require new data centers to use over 80% green power; green power direct-connect projects must self-generate and self-use at least 60% of electricity. - 200MW (about 100,000 GPUs) is feasible for a single site, but 800MW is still exploratory; grid connection cycles take 2-3 years. ### Why it matters to ebm-papst Assessment (inference): The shift to 800V DC and SST in AIDC power architectures signals a major market transition that could impact ebm-papst's traditional AC fan and motor products. As data centers move towards higher voltage DC distribution, there may be increased demand for DC-powered cooling solutions and high-efficiency fans that can operate reliably under fluctuating power conditions. ebm-papst should monitor these developments to adapt its product portfolio, potentially developing DC-compatible fans and motors that meet the stringent efficiency and reliability requirements of next-gen AIDCs. Additionally, the emphasis on energy storage and grid stability may create opportunities for ebm-papst in thermal management of storage systems. The company's expertise in high-efficiency EC fans could be leveraged to support the cooling needs of high-density racks and energy storage systems, positioning ebm-papst as a key partner in the evolving AIDC ecosystem.
原文全文
原文
英文翻译
人工智能进入规模化应用阶段后,算力基础设施正面临前所未有的供电压力。单机柜功率已从早期通算的10kW攀升至智算阶段的140kW,下一代AI服务器更规划至200kW甚至300kW。
与此同时,GPU负载特性进一步放大挑战:从Volta时代的峰值155%(0.5ms以内),到Hopper的180%,再到Blackwell(GB300系列)的200%以上,稳态精度要求也从±10%收紧至±5%,供电架构从"配套设施"跃升为AIDC规模化落地的核心约束。
在2026中国智算产业生态发展大会上,腾讯数据中心专家工程师张佳斌指出,GPU并行架构导致任务启停瞬间剧烈波动,且同一集群服务器功率变化趋势高度同步,"整个IDC变成了一台电脑",数十兆瓦乃至上百兆瓦的功率波动对电网、柴发和蓄电池形成直接冲击。传统交流UPS链路在效率、空间与可靠性上的瓶颈已充分显现。
高压直流当前似乎已经成为行业共识,电池直接挂母线带来的可靠性、故障域可控与模块级可维护性、以及能效提升这些优势毋庸置疑。特别是在高密需求下,传统供配电单体积来讲就将占据超过50%的机柜空间。
但商用高压直流仍面临功率密度偏低(单柜仅150kW量级)、厂家差异大、运维复杂、效率被UPS反超等问题。
★演进路径:从过渡方案到设施级重构
行业正形成多层次并行路径,目前有四条主流技术路线:
★PowerRack/Sidecar:10kV经工频变压器至400V,再整流输出800V直流,当前成熟度相对较高;
★巴拿马电源(DCUPS):移相变压器去除PFC,经正负极串联实现800V;
★一体化直流电源Pod:模块内优化AC输入电压,兼顾效率与铜材;
★SST(固态变压器):10kV直接电力电子变换至800V,被视为"终极形态"。
广东智光综合能源数据中心业务部解决方案总监纪铎鹏进一步指出,供电架构正从传统交流UPS、基础直流240V、集成化巴拿马电源,最终走向800V固态变压器。政策层面,国家枢纽节点要求新建数据中心绿电占比超过80%,绿电直连项目自发自用电量不低于60%,"十五五"规划明确算电协同方向。面对高功率、高容量、高波动三大挑战,SST通过省去工频变压器与多级变换,可提升效率4%以上,占地面积节省60%以上,架构简洁、故障节点减少。智光Coota1.0产品实现10kV至800V一步变换,整机效率达98.5%,容量覆盖1MW–4.2MW,并支持双向能量调度与构网能力。
SST与800V并非强绑定。张佳斌强调:"800V不一定非要有SST来实现,SST也并非只能适用于800V场景,它们是独立演进的技术体系,只是恰好在IDC交汇。"并指出,核心卡点在于800V整流模块的数据中心级定制,以及被忽视的800V配电与末端配电产品成熟度。 ★系统级应对:储能、波动与全链路协同
功率波动的治理需分层储能,专家介绍,当前主要是三级方案:
★园区集群级:MW级大储,应对园区整体负荷波动;
★电源级:UPS/高压直流输入或输出侧超级电容与AC/DC补偿,应对电源侧瞬态;
★服务器级:CBU与电解电容,应对服务器内部毫秒级波动。
OpenAI、微软、谷歌联合论文亦将储能列为主流路径,软件假负载与人工降功率则因性能损失难以接受。实际测试显示,常用1800kW柴发在负荷突变超过约10%时即难以满足国标频率振荡恢复要求;GPU机房蓄电池健康问题比例显著偏高,频繁充放电加速硫酸盐化,寿命可能从五年缩短至三年以内。
纪铎鹏补充级联型高压直挂储能可直挂6–36kV电网,单机响应≤5ms,系统效率达92%,较传统低压储能高出6–10个百分点,适配高动态、脉冲式算力负载,并支持无缝离并网与备用电源功能。在绿电直连场景下,SST+级联高压储能可构建源网荷储一体化,实现全链条溯源、降低输配电费并提升新能源消纳。
★产业观察:从单点突破到生态重构
美的楼宇科技战略业务总经理杨鹏宇已预警,800V电力系统变化对操作、安全、保护提出更苛刻要求,风液共存仍将长期存在,制冷评价正从"降温精度"转向"释放算力"与Token产出。科智咨询报告亦将液冷、HVDC与算电协同列为加速落地的技术方向。
润泽科技副总经理兼首席技术官沈诚从GW级集群视角指出,单体200MW(约10万卡)已可落地,800MW仍属探索,电、水、政策与配网周期(2–3年)成为硬约束;核电直供、钍基熔盐等远期电源方案进入讨论。
当前800V仍处工程化攻坚阶段。安全维护(防护装备、电工资质)、功率器件电压等级、行业标准与规范尚不完善。张佳斌坦言,800V配电与末端产品是"现在的盲点"。与此同时,新能源与电动汽车带来的800V器件与高能效技术红利正在向数据中心溢出,全产业链协同(电源、配电、服务器)成为必要条件。
★效率、空间与确定性的平衡
800V并非单纯电压升级,而是从机柜内部电源空间争夺、集群功率波动治理,到园区级能源路由与绿电消纳的系统性重构。过渡期PowerRack/Sidecar与巴拿马方案提供快速落地路径,SST则代表设施级简化与效率上限。储能分层、直流可靠性优势与算电协同政策,共同构成落地支撑。
产业共识正在形成:供电架构必须与机柜功率密度、GPU负载特性、绿电比例同步演进。真正的考验在于工程可靠性、标准统一与全生命周期成本——让每一瓦电力更高效地转化为可用算力与Token产出。这一进程,将直接决定AIDC从"能建"走向"建得好、用得稳、算得经济"的速度。
After AI enters the stage of large-scale application, computing infrastructure is facing unprecedented power supply pressure. Single-rack power has risen from 10kW in early general computing to 140kW in the intelligent computing stage, and next-generation AI servers are planned to reach 200kW or even 300kW.
At the same time, GPU load characteristics further amplify the challenges: from a peak of 155% (within 0.5ms) in the Volta era, to 180% in Hopper, and over 200% in Blackwell (GB300 series), steady-state accuracy requirements have also tightened from ±10% to ±5%. The power supply architecture has escalated from a 'supporting facility' to a core constraint for large-scale AIDC deployment.
At the 2026 China Intelligent Computing Industry Ecosystem Development Conference, Zhang Jiabin, a senior expert engineer at Tencent Data Center, pointed out that GPU parallel architecture causes severe fluctuations during task start/stop, and power consumption trends of servers in the same cluster are highly synchronized, 'turning the entire IDC into a single computer,' with tens to hundreds of megawatts of power fluctuations directly impacting the grid, diesel generators, and batteries. The bottlenecks of traditional AC UPS chains in efficiency, space, and reliability have become fully apparent.
High-voltage DC currently seems to have become an industry consensus. The advantages of directly connecting batteries to the busbar, such as reliability, controllable fault domains, module-level maintainability, and energy efficiency improvements, are undeniable. Especially under high-density requirements, traditional power distribution and distribution units alone can occupy over 50% of cabinet space.
However, commercial high-voltage DC still faces issues such as low power density (only around 150kW per cabinet), significant vendor differences, complex operation and maintenance, and efficiency being overtaken by UPS.
★Evolution path: from transitional solutions to facility-level reconstruction
The industry is forming a multi-level parallel path, with four mainstream technical routes currently:
★PowerRack/Sidecar: 10kV is transformed to 400V via a power frequency transformer, then rectified to 800V DC. Current maturity is relatively high.
★Panama Power (DCUPS): Phase-shifting transformer removes PFC, achieving 800V through series connection of positive and negative poles.
★Integrated DC Power Pod: Optimizes AC input voltage within the module, balancing efficiency and copper usage.
★SST (Solid-State Transformer): Direct power electronic conversion from 10kV to 800V, regarded as the 'ultimate form.'
Ji Duopeng, Director of Data Center Business Solutions at Guangdong Zhiguang Integrated Energy, further pointed out that the power supply architecture is evolving from traditional AC UPS, basic 240V DC, integrated Panama Power, and ultimately to 800V solid-state transformers. At the policy level, national hub nodes require new data centers to have green power ratio exceeding 80%, and green power direct-connect projects must have self-generated and self-consumed electricity not less than 60%. The '15th Five-Year Plan' clearly defines the direction of computing-power coordination. Facing the three major challenges of high power, high capacity, and high fluctuation, SST can improve efficiency by more than 4% and save over 60% floor space by eliminating power frequency transformers and multi-stage conversion, with a simpler architecture and fewer fault nodes. Zhiguang's Coota1.0 product achieves one-step conversion from 10kV to 800V, with overall efficiency of 98.5%, capacity covering 1MW–4.2MW, and supports bidirectional energy scheduling and grid-forming capability.
SST and 800V are not strongly bound. Zhang Jiabin emphasized: '800V does not necessarily require SST to be implemented, and SST is not only applicable to 800V scenarios. They are independently evolving technology systems that happen to intersect in IDC.' He also pointed out that the core bottleneck lies in the data center-level customization of 800V rectifier modules, as well as the overlooked maturity of 800V distribution and end-of-line products.
★System-level response: energy storage, fluctuation, and full-chain collaboration
The governance of power fluctuations requires layered energy storage. Experts introduced that the current main approach is a three-level scheme:
★Campus cluster level: MW-level large storage to handle overall campus load fluctuations.
★Power supply level: Supercapacitors and AC/DC compensation on the input or output side of UPS/HVDC to handle transient power supply side.
★Server level: CBU and electrolytic capacitors to handle millisecond-level fluctuations inside servers.
A joint paper by OpenAI, Microsoft, and Google also lists energy storage as a mainstream path, while software dummy loads and manual power reduction are unacceptable due to performance loss. Actual tests show that common 1800kW diesel generators struggle to meet national standard frequency oscillation recovery requirements when load changes exceed about 10%. GPU room battery health issues are significantly higher, with frequent charge/discharge accelerating sulfation, potentially shortening lifespan from five years to less than three years.
Ji Duopeng added that cascaded high-voltage direct-mounted storage can be directly connected to 6–36kV grids, with single-unit response ≤5ms, system efficiency of 92%, 6–10 percentage points higher than traditional low-voltage storage, suitable for high-dynamic, pulsed computing loads, and supports seamless off-grid and backup power functions. In green power direct-connect scenarios, SST + cascaded high-voltage storage can build an integrated source-grid-load-storage system, achieving full-chain traceability, reducing transmission and distribution fees, and enhancing renewable energy consumption.
★Industry observation: from single-point breakthroughs to ecosystem reconstruction
Yang Pengyu, General Manager of Strategic Business at Midea Building Technology, has warned that 800V power system changes impose more stringent requirements on operation, safety, and protection. Air and liquid cooling will coexist for a long time, and cooling evaluation is shifting from 'cooling precision' to 'releasing computing power' and Token output. Kezhi Consulting's report also lists liquid cooling, HVDC, and computing-power coordination as technology directions accelerating deployment.
Shen Cheng, Deputy General Manager and CTO of Runze Technology, viewed from a GW-level cluster perspective that a single 200MW (about 100,000 GPUs) is already feasible, while 800MW is still exploratory. Electricity, water, policy, and grid connection cycles (2–3 years) become hard constraints; nuclear power direct supply, thorium-based molten salt, and other long-term power sources are entering discussions.
Currently, 800V is still in the engineering hardening stage. Safety maintenance (protective equipment, electrician qualifications), power device voltage levels, and industry standards and specifications are not yet complete. Zhang Jiabin admitted that 800V distribution and end-of-line products are 'the current blind spot.' At the same time, the dividends of 800V devices and high-efficiency technologies from new energy and electric vehicles are spilling over to data centers, making full-chain collaboration (power supply, distribution, servers) a necessary condition.
★Balance of efficiency, space, and certainty
800V is not simply a voltage upgrade, but a systematic reconstruction from power space competition inside the cabinet, cluster power fluctuation governance, to campus-level energy routing and green power consumption. During the transition period, PowerRack/Sidecar and Panama solutions provide rapid deployment paths, while SST represents facility-level simplification and efficiency ceiling. Layered energy storage, DC reliability advantages, and computing-power coordination policies together form the foundation for implementation.
Industry consensus is forming: the power supply architecture must evolve in sync with cabinet power density, GPU load characteristics, and green power ratio. The real test lies in engineering reliability, standard unification, and full lifecycle cost—making every watt of electricity more efficiently converted into usable computing power and Token output. This process will directly determine the speed at which AIDC moves from 'can build' to 'build well, use stably, and compute economically.'