# Youyan New Material Invests 486M RMB to Expand High-Purity Sputtering Target Capacity for ICs, Adding 30,000 Units/Year

- Source: JW Insights (T2)
- Published: 2026-01-01
- Score: 30.0
- Tags: Capacity, Cleanroom
- Original: https://www.laoyaoba.com/n/1073305

## Intelligence brief

### What happened On July 30, 2026, Youyan New Material Co., Ltd. (Youyan New Material) announced a second-phase expansion project for high-purity sputtering targets used in integrated circuits. The project will be undertaken by its subsidiary Youyan Yijin New Material (Shandong) Co., Ltd. at the existing plant site in Dezhou, Shandong Province. The expansion aims to address near-capacity utilization of the current copper and tantalum target production lines, driven by recovering global semiconductor demand. The new facility will cover approximately 16,500 square meters and include production lines for high-purity copper and copper alloy targets, tantalum targets, and titanium targets. Construction is scheduled to start in September 2026, with production launch in September 2027 and full investment completion by December 2028. The project has been approved by the company's strategic committee and board of directors. ### Key figures - Total investment: 486 million RMB (approx. 67 million USD) - New capacity: 30,000 high-end sputtering targets per year - New building area: ~16,500 square meters - Construction start: September 2026 - Production launch: September 2027 - Investment completion: December 2028 - Funding source: Own funds or self-raised ### Why it matters to ebm-papst This expansion signals growing demand for advanced semiconductor manufacturing equipment and cleanroom infrastructure in China. As Youyan New Material ramps up target production, fab construction and upgrades will require high-performance fans and motors for cleanroom HVAC, process cooling, and exhaust systems. ebm-papst's energy-efficient EC fans and corrosion-resistant motors are well-positioned to serve these applications. Assessment (inference): The project timeline (2026-2028) aligns with ebm-papst's product development cycles, presenting a potential sales opportunity if the company can engage with fab builders and equipment OEMs early. However, the investment is modest compared to major fab projects, so the direct impact on ebm-papst's revenue may be limited. The focus on 7nm and below process nodes implies stricter cleanroom standards, which could drive demand for higher-performance air handling units where ebm-papst's premium products compete.

## Full text (English translation)

On July 30, 2026, Youyan New Material announced a second-phase expansion project for high-purity sputtering targets used in integrated circuits.

With the recovery and expansion of the global semiconductor industry, demand for semiconductor targets is growing. The company's existing Dezhou base's copper and tantalum target production capacity is nearing saturation, and a capacity gap will emerge. To address this, the company plans to launch this expansion project to further optimize product structure, add 30,000 high-end targets per year, achieve mass production, and increase the domestic substitution rate.

The project will be undertaken by Youyan Yijin New Material (Shandong) Co., Ltd. at the reserved land within the existing plant site. This is a fixed asset investment for operational purposes. A new factory building of approximately 16,500 square meters will be constructed, along with production lines for high-purity copper and copper alloy targets, tantalum targets, and titanium targets. The project is scheduled to start construction in September 2026, begin production in September 2027, and complete investment by December 2028. The total investment is 486 million RMB, funded by own or self-raised capital.

This expansion project focuses on core materials for integrated circuits and is compliant with policies and eligible for support. After implementation, it will increase the company's relevant target production capacity, raise the domestic substitution rate of high-end sputtering targets in China, and overcome technical bottlenecks in target preparation for advanced process nodes below 7nm.

The project may face risks such as changes in macroeconomic policies and market competition. The company has established corresponding response mechanisms. There may also be risks that construction progress, capacity, revenue, and profit fall short of expectations.

On July 30, 2026, the company's strategic committee and board of directors both reviewed and approved the project feasibility study report.

The project complies with national industrial policies and the company's strategy and is fully feasible.

## Full text (original)

2026年07月30日，有研新材发布集成电路用高纯溅射靶材二期扩建项目的公告。
随着全球半导体产业复苏与扩张，半导体靶材需求增长，公司现有德州基地铜系、钽系靶材产能接近饱和，将现产能缺口。为此，公司计划推出该扩建项目，进一步优化产品结构，新增高端靶材产能30,000块/年，实现规模化量产，提高国产化率。
项目承建单位为有研亿金新材料(山东)有限公司，地点在现有厂区预留地。该项目属经营性固定资产投资，新建1座约1.65万平方米厂房，建设高纯铜及铜合金靶、钽靶、钛靶等产线。项目计划于2026年9月启动建设，2027年9月投产释放产能，2028年12月投资完成，总投资4.86亿元，资金来自自有或自筹。
此扩产项目聚焦集成电路核心材料，具政策合规性与扶持适配性。实施后将提升公司相关靶材产能，提升我国高端溅射靶材国产化率，攻克7nm以下先进制程靶材制备技术瓶颈。
项目可能存在宏观经济政策、市场竞争格局变化等风险，公司建立相应应对机制。还可能存在建设进度、产能、营收及利润不及预期风险。
2026年7月30日，公司战略委员会和董事会均审议通过项目可行性研究报告。
项目符合国家产业政策和公司战略，具备全面可行性。