What happened In 2026, the power semiconductor market is experiencing a stark contrast: surging demand from AI data centers and new energy vehicles is widening the MOSFET supply-demand gap, while overseas IDM leaders have raised prices and extended lead times to 30–50 weeks, with some reaching nearly 10 months. Against this backdrop, Nexperia China, a veteran automotive-grade IDM with European heritage, has taken a contrarian approach by maintaining stable prices and guaranteeing 8-week delivery for its MOSFET products. The company has completed a localized supply chain transformation, leveraging domestic 12-inch wafer partners and a large-scale backend packaging and testing facility in Dongguan, achieving full local production. This allows Nexperia China to decouple from overseas allocation constraints and offer competitive pricing and short lead times to all customers, regardless of order size. ### Key figures - Overseas IDM lead times: 30–50 weeks, with some high-voltage devices up to 52 weeks. - Nexperia China MOSFET delivery: 8 weeks (regular part numbers). - Price increases: Infineon announced a second price hike of 10–20% effective July 1, 2026; Texas Instruments initiated its second round of price adjustments in 2026; STMicroelectronics implemented its second wave of increases on June 28, 2026. - 8-inch wafer foundry utilization: TrendForce estimates 2026 average utilization will rise to 85–90%, up from 75–80% in 2025, with some foundries raising prices by 5–20%. - 12-inch wafer die count: 2.25 times that of 8-inch wafers. - Yole forecast: By 2026, automotive will become the largest MOSFET application market, accounting for 33% of total demand. - No specific figures disclosed for Nexperia China's capacity or market share. ### Why it matters to ebm-papst Nexperia China's strategy directly addresses the pain points of downstream manufacturers, including those in the industrial control, power supply, and automotive sectors—key customer segments for ebm-papst. Stable MOSFET supply and pricing can reduce cost pressures for ebm-papst's customers, potentially increasing demand for ebm-papst's fans and motors in applications like EV thermal management, industrial ventilation, and server cooling. However, if Nexperia China's MOSFETs enable more competitive end products, it could intensify price competition among ebm-papst's customers, indirectly pressuring ebm-papst's margins. Assessment (inference): Nexperia China's move signals a structural shift in the power semiconductor supply chain, favoring localized production and shorter lead times. This could reduce the dependency on overseas IDMs and mitigate supply risks for ebm-papst's supply chain. However, if the trend accelerates, ebm-papst may need to evaluate its own component sourcing strategy to leverage similar localized alternatives for cost and reliability benefits.
原文全文
原文
英文翻译
2026年的功率半导体市场,正经历着一场罕见的“冰火两重天”。
一边是AI数据中心、新能源车需求持续井喷,MOSFET供需缺口越撕越大;另一边是海外IDM龙头接连涨价、交期拉长至30到50周,最长逼近十个月。这让下游为数众多的国内车企、Tier1供应商、工控电源和供电系统制造企业,苦不堪言。
海外大厂涨价的逻辑,其实不难理解
先看现状。2026年开年以来,功率半导体已经历了两轮涨价。英飞凌5月底再次发出涨价函,宣布自7月1日起二次提价,幅度10%至20%,覆盖AI电源芯片、车规IGBT和MOSFET;德州仪器同步启动年内第二轮调价;意法半导体6月28日实施2026年第二波调涨。
交期方面同样不容乐观。主流功率半导体交付周期已普遍拉长至30周以上,部分高压器件更长。低压MOSFET的交付周期从去年四季度的12到40周,拉长到12至52周甚至更久。
这一轮缺货涨价,底层逻辑其实有四层
第一,晶圆产能彻底触顶。多年来海外大厂不愿对8英寸产线新增大规模投资,传统硅基功率器件长期毛利偏低,缺乏扩产动力。仅存的8英寸产能不断转向碳化硅等第三代半导体,而新增的12英寸产线产能基本被利润更高的电源管理IC(PMIC)占据。TrendForce预估,2026年全球8英寸晶圆代工厂平均产能利用率将从2025年的75%至80%大幅攀升至85%至90%,部分晶圆厂已通知客户调涨代工价5%至20%。
第二,地缘环境打乱全球供应链。跨国调货壁垒变高,海外总部不会为亚太区灵活调配库存与产能,国内市场很难拿到稳定配额。
第三,海外集团统一管控,区域没有自主调整空间。所有定价、排产、产能计划全部由海外总部统一决策,亚太区没有权限根据本地行情灵活应对。
第四,新兴产业全面扩容。新能源车、AI服务器、人形机器人、动力电池、储能系统等需求爆发。单台AI服务器对高压MOSFET的需求大幅增长,进一步加剧了8英寸产能的紧缺。Yole预测,到2026年汽车将晋级为MOSFET最大应用市场,合计占比达33%。
但行业有一个隐藏的深层矛盾:AI一路高歌,其余赛道内卷严重
当下整个半导体行业,只有AI产业链可以轻松承接元器件涨价带来的成本压力。反观新能源配套、电池保护、工控电源、人形机器人、消费电子产业,虽然整体需求量逐年上涨,但终端产品售价持续下行。
以新能源汽车为例——整个赛道规模持续扩张,产销不断创下新高,可车企的整体净利润却连年下滑。车企面临三重硬性要求:需求量持续增加,车规级品质标准不能有半点降低,元器件采购价格必须具备足够竞争力,供应链必须稳定可靠。
下游制造企业两头承压:一边原厂不断涨价、拉长交期,一边下游终端利润微薄。整个产业链都在迫切寻找稳定、平价、高品质的MOS替代方案。
安世中国的“逆势操作”:本土化产能改写行业规则
但就在全行业涨价声一片的背景下,有一家老牌车规IDM却走出了完全相反的路线——不涨价、保8周交付。
这不是某个初创企业的营销口号,而是一家拥有数十年欧洲车规半导体底蕴、刚刚完成本土化供应链重塑的巨头,正在做的事。
安世中国作为完成本土化转型的老牌IDM,跳出了行业涨价周期。
这家拥有欧洲数十年车规半导体底蕴的企业,早年和所有海外大厂一样受制于海外总部的统一调度。但经过近期的本土化供应链重塑,情况彻底变了。
目前,安世中国已经彻底摆脱海外体系约束,依托国内12英寸晶圆合作伙伴、东莞规模化封测基地,整体产能大幅扩充,拥有了逆势操作的底气。更关键的是技术路线的代际超越。和海外大厂死守老旧8英寸产线不同,安世中国全面切换12英寸车规功率工艺。单张12英寸晶圆的裸片总数达到8英寸的2.25倍,产能高出一倍以上;新一代工艺良率远超老旧8英寸产线,制造成本大幅下降。
后端东莞封测工厂全年满产,晶圆制造、封测、测试全部实现本土闭环,不再受制于海外排产与国际物流。
基于充足的本土产能,安世中国做出了和所有海外大厂完全相反的选择:在全行业涨价的环境下,MOS产品价格稳定,常规料号保持8周交付,面向所有客户平价锁量保供,不分长协大客户与中小厂商。
为什么这套方案更受行业认可?
不少硬件工程师和采购已经开始系统整理对标清单,把安世中国主力MOS料号和英飞凌、安森美最常用的十大流量型号做一一对标——覆盖封装、关键电气参数、损耗特性、温度特性、长期价格走势。从实测数据来看,对应料号做到了完全PIN TO PIN兼容,在参数、可靠性、车规等级层面和英飞凌、安森美处于同一水准,部分指标甚至更优。
很多人会产生疑问:扩产的厂商不少,为什么这套方案更受行业认可?
核心在于底层的品质积累。安世器件长期大批量供给欧美车企、全球服务器、海外工业龙头,严苛的AEC-Q100车规标准、零缺陷管控体系延续至今。对于工控、汽车电源、服务器电源这类对稳定性要求极高的场景,经过长年批量验证的老牌IDM产品,远比单纯低价的器件更加稳妥。
当下半导体市场冷暖分化,本质是不同应用赛道的内卷程度、成本承受能力存在巨大差距。少数高景气赛道能够接纳元器件涨价,但绝大多数中下游制造企业无力消化持续抬升的物料成本。
在这个背景下,安世中国选择逆势让利——依靠充足产能和一流的车规品质,精准解决了行业大规模供货、控成本、保品质的核心痛点。安世中国的选择,或许正是2026年功率半导体行业最有意思的一个变量。
The power semiconductor market in 2026 is experiencing a rare "ice and fire" situation.
On one hand, demand from AI data centers and new energy vehicles continues to surge, widening the MOSFET supply-demand gap; on the other hand, overseas IDM leaders have successively raised prices and extended lead times to 30 to 50 weeks, with the longest approaching ten months. This has caused great suffering for many domestic automakers, Tier 1 suppliers, industrial control power supplies, and power system manufacturers.
The logic behind overseas manufacturers' price increases is not hard to understand.
First, look at the current situation. Since the beginning of 2026, power semiconductors have experienced two rounds of price increases. Infineon issued another price hike letter at the end of May, announcing a second price increase of 10% to 20% effective July 1, covering AI power chips, automotive IGBTs, and MOSFETs; Texas Instruments simultaneously initiated its second round of price adjustments for the year; STMicroelectronics implemented its second wave of increases for 2026 on June 28.
Lead times are also not optimistic. The delivery cycle for mainstream power semiconductors has generally extended to over 30 weeks, with some high-voltage devices taking even longer. The delivery cycle for low-voltage MOSFETs has lengthened from 12 to 40 weeks in Q4 last year to 12 to 52 weeks or even longer.
There are four underlying reasons for this shortage and price increase.
First, wafer capacity has completely hit the ceiling. Overseas manufacturers have been unwilling to invest heavily in new 8-inch production lines for years, as traditional silicon-based power devices have long had low gross margins and lack expansion incentives. The remaining 8-inch capacity is continuously shifting to third-generation semiconductors like silicon carbide, while new 12-inch production lines are mostly occupied by higher-margin power management ICs (PMICs). TrendForce estimates that the average capacity utilization rate of global 8-inch wafer foundries in 2026 will rise sharply from 75% to 80% in 2025 to 85% to 90%, and some foundries have notified customers of foundry price increases of 5% to 20%.
Second, the geopolitical environment has disrupted global supply chains. Cross-border allocation barriers have become higher, overseas headquarters are not flexible in allocating inventory and capacity for the Asia-Pacific region, and the domestic market finds it difficult to obtain stable quotas.
Third, overseas groups have unified control, leaving no room for regional adjustments. All pricing, production scheduling, and capacity plans are decided by overseas headquarters, and the Asia-Pacific region has no authority to respond flexibly based on local market conditions.
Fourth, emerging industries are expanding comprehensively. Demand from new energy vehicles, AI servers, humanoid robots, power batteries, and energy storage systems is exploding. The demand for high-voltage MOSFETs in a single AI server has increased significantly, further exacerbating the shortage of 8-inch capacity. Yole predicts that by 2026, automotive will become the largest application market for MOSFETs, accounting for 33% of total demand.
But there is a hidden deep contradiction in the industry: AI is booming, while other tracks are fiercely competitive.
Currently, only the AI supply chain in the entire semiconductor industry can easily absorb the cost pressure from component price increases. In contrast, industries such as new energy supporting, battery protection, industrial control power supplies, humanoid robots, and consumer electronics, although overall demand is rising year by year, terminal product prices continue to decline.
Take new energy vehicles as an example—the entire track is expanding, production and sales continue to hit new highs, but the overall net profit of automakers has been declining year after year. Automakers face three hard requirements: continuously increasing demand, no reduction in automotive-grade quality standards, competitive component procurement prices, and stable and reliable supply chains.
Downstream manufacturers are under pressure from both sides: on one hand, original manufacturers keep raising prices and extending lead times; on the other hand, downstream terminal profits are thin. The entire industry chain is urgently seeking stable, affordable, and high-quality MOS alternatives.
Nexperia China's "contrarian operation": localized capacity rewrites industry rules.
But against the backdrop of industry-wide price increases, one veteran automotive-grade IDM has taken a completely opposite path—no price increases, guaranteed 8-week delivery.
This is not a marketing slogan from a startup, but something being done by a giant with decades of European automotive semiconductor heritage that has just completed a localized supply chain transformation.
Nexperia China, as a veteran IDM that has completed its localization transformation, has broken away from the industry's price increase cycle.
This company, with decades of European automotive semiconductor heritage, was once subject to unified scheduling by overseas headquarters like all other overseas manufacturers. But after a recent localized supply chain transformation, the situation has completely changed.
Currently, Nexperia China has completely shed the constraints of the overseas system. Relying on domestic 12-inch wafer partners and a large-scale packaging and testing base in Dongguan, overall capacity has been greatly expanded, giving it the confidence to operate contrarily. More importantly, there is a generational leap in technology roadmap. Unlike overseas manufacturers clinging to old 8-inch production lines, Nexperia China has fully switched to 12-inch automotive-grade power processes. The total number of dies on a single 12-inch wafer is 2.25 times that of an 8-inch wafer, more than doubling capacity; the yield of the new generation process far exceeds that of old 8-inch lines, significantly reducing manufacturing costs.
The backend Dongguan packaging and testing factory operates at full capacity throughout the year, achieving a complete local闭环 from wafer manufacturing, packaging, testing to final test, no longer constrained by overseas scheduling and international logistics.
Based on sufficient local capacity, Nexperia China has made a choice completely opposite to all overseas manufacturers: in an environment of industry-wide price increases, MOS product prices remain stable, regular part numbers maintain 8-week delivery, and all customers—whether long-term contract large customers or small and medium-sized manufacturers—are offered stable pricing and guaranteed supply.
Why is this solution more recognized by the industry?
Many hardware engineers and procurement professionals have begun systematically compiling comparison lists, matching Nexperia China's main MOS part numbers with the ten most commonly used models from Infineon and ON Semiconductor—covering packaging, key electrical parameters, loss characteristics, temperature characteristics, and long-term price trends. From measured data, the corresponding part numbers are fully PIN TO PIN compatible, with parameters, reliability, and automotive-grade levels on par with Infineon and ON Semiconductor, and some indicators even better.
Many people wonder: many manufacturers are expanding capacity, so why is this solution more recognized by the industry?
The core lies in the underlying quality accumulation. Nexperia devices have long been supplied in large quantities to European and American automakers, global servers, and overseas industrial leaders, with strict AEC-Q100 automotive standards and a zero-defect control system continuing to this day. For applications such as industrial control, automotive power supplies, and server power supplies that require high stability, products from veteran IDMs with years of batch verification are far more reliable than simply low-cost devices.
The current divergence in the semiconductor market essentially reflects the huge differences in the degree of competition and cost tolerance across different application tracks. A few high-prosperity tracks can accommodate component price increases, but the vast majority of midstream and downstream manufacturers cannot afford to continuously absorb rising material costs.
In this context, Nexperia China has chosen to go against the trend and make concessions—relying on sufficient capacity and first-class automotive-grade quality to precisely solve the core pain points of large-scale supply, cost control, and quality assurance in the industry. Nexperia China's choice may be the most interesting variable in the 2026 power semiconductor industry.