What happened Melbourne has overtaken Sydney as the largest data center development pipeline in Australia, according to the October edition of a joint report by DC Byte and Data Centres Australia, reported by Data Center Knowledge on 20 November 2026. The shift reflects AI-driven demand, power constraints in established hubs, and differing state planning regimes that are steering new projects toward Victoria and regional markets. Melbourne's tracked capacity rose by 1.7 GW to 10.7 GW between the April and October editions of the report, while Sydney's fell by 3.6 GW to 7.8 GW. Nationally, total tracked capacity — operational facilities plus projects at every development stage — increased by 5.2 GW to 26.8 GW, but operational capacity rose by only 0.1 GW to 1.6 GW, highlighting the gap between campus announcements and usable infrastructure. Sydney's decline was driven largely by withdrawn or revised early-stage proposals, with growth in committed capacity partly offsetting the drop. Melbourne moved 1.2 GW into committed capacity during the period, versus 0.7 GW in Sydney. DC Byte's Teresa Tan attributed part of Melbourne's momentum to Victoria's Development Facilitation Pathway, while JLL's Matthew Lee cited AI demand. The report also flagged new Victorian state policies and an apparent pause in approvals ahead of the November election as factors that could affect future forecasts. ### Key figures - Melbourne tracked capacity: up 1.7 GW to 10.7 GW (April to October 2026) - Sydney tracked capacity: down 3.6 GW to 7.8 GW - National tracked capacity: up 5.2 GW to 26.8 GW - National operational capacity: up 0.1 GW to 1.6 GW - Early-stage proposals: 19.6 GW, about 73% of the national total - Capacity under construction: 0.4 GW - Proposed projects above 100 MW: 52; operating facilities above 100 MW: 4 - Operational facilities tracked: 163; proposed new projects: 97 (seven more than April) - Sydney early-stage capacity: down from 8.6 GW to 4.2 GW; committed capacity up from 1.9 GW to 2.6 GW - Operational capacity: Sydney 0.9 GW vs Melbourne 0.5 GW - Melbourne early-stage capacity: up 0.3 GW to 7.8 GW - National committed capacity: up from 3.1 GW to 5.2 GW - New South Wales framework: qualifying projects assessed within 75 days - 2030 forecast: 3.9 GW operational nationally; Sydney 2.0 GW, Melbourne 1.4 GW, combined about 3.4 GW - Forecast trajectory: 1.8 GW end-2026, 2.3 GW 2027, 2.7 GW 2028, 3.4 GW 2029, 3.9 GW 2030 - Regional share of pipeline: 31%, up from 19% two years ago - Regional early-stage additions: New South Wales 1.3 GW, Victoria 0.7 GW - Customer commitments: about 90% of operational and under-construction capacity ### Why it matters to ebm-papst Australia's pipeline is expanding far faster than its operational base, and the binding constraint is shifting from generation to site-level grid connection. For ebm-papst, this is primarily a demand-timing signal rather than an immediate volume opportunity: 19.6 GW of early-stage proposals and only 0.4 GW under construction means cooling and air-movement orders will be spread over years and remain contingent on energization dates, transmission works, and terminal-station schedules. Melbourne's rise and the regional shift — 31% of the pipeline now outside Sydney and Melbourne, with interest around Morwell, Western Australia, and Queensland — imply a more dispersed project map. That favors suppliers with local application engineering and service coverage rather than pure product logistics. The 2030 forecast of 3.9 GW fitted IT capacity, with Sydney still ahead at 2.0 GW despite Melbourne's larger pipeline, suggests near-term retrofit and phased-build demand in Sydney alongside greenfield work in Victoria. Assessment (inference): ebm-papst's most defensible play is to position fan and cooling solutions around high-density AI halls in the committed 5.2 GW tranche, where customer pre-commitment is around 90%, rather than chasing early-stage announcements. Assessment (inference): the connection bottleneck and staffing limits in regional sites could favor modular, prefabricated cooling architectures that reduce on-site labor. Assessment (inference): Australia's cost disadvantage versus other Asia-Pacific markets may cap hyperscale training demand, so sovereign, regulated, and inference workloads are the more reliable segment to target.
原文全文
- Data Center Site Selection
- Data Center Construction
- Energy & Power Supply
- AI Data Centers
- Industry Trends
Melbourne Overtakes Sydney in Australia’s Data Center Pipeline
Melbourne now leads Australia’s data center pipeline, but power connections will determine how much capacity actually comes online.
Melbourne has overtaken Sydney in Australia’s data center development pipeline, with AI demand, power constraints, and planning conditions shifting new projects toward Victoria and regional markets. But most of that proposed capacity remains years away from operation.
Melbourne’s tracked capacity rose by 1.7 GW to 10.7 GW between the April and October editions of a report from DC Byte and Data Centres Australia, while Sydney’s fell by 3.6 GW to 7.8 GW.
Nationally, total tracked capacity – including operational facilities and projects at every stage of development – increased by 5.2 GW to 26.8 GW. But operational capacity rose by just 0.1 GW to 1.6 GW, underscoring the gap between large campus announcements and usable computing infrastructure.
DC Byte tracked 163 operational facilities and 97 proposed new projects, seven more than in April. Of those proposed projects, 52 have announced capacity above 100 MW. By comparison, only four operating facilities currently exceed that threshold.
Early-stage proposals accounted for 19.6 GW, or about 73% of the national total. Just 0.4 GW was under construction, a category DC Byte defines as data halls undergoing mechanical and electrical fit-out.
Teresa Tan, DC Byte’s lead analyst for Asia-Pacific, said the gap reflects the way projects enter the pipeline and progress through construction.
“A developer can add an entire campus to the pipeline in one update, but from an executional perspective, capacity comes online one data hall at a time,” she told Data Center Knowledge.
About 2.8 GW of the net increase came from early-stage capacity, where project sizes and schedules remain most susceptible to change.
“Some of that capacity will take years to deliver, while other proposals may never proceed,” Tan added.
Sydney’s Early-Stage Pipeline Shrinks
Sydney’s shrinking pipeline does not indicate a similar retreat in projects nearing delivery. Tan said the drop was driven largely by withdrawn or revised early-stage proposals, with growth in committed capacity partly offsetting it.
Early-stage capacity in Sydney fell from 8.6 GW to 4.2 GW, while committed capacity rose from 1.9 GW to 2.6 GW. Sydney still retained more operational capacity than Melbourne, at 0.9 GW versus 0.5 GW.
Matthew Lee, executive director and co-head of Australian data centers at JLL, said Sydney remains a priority for investors, developers, and customers despite ongoing power and planning constraints.
“Any shift in pipeline is not likely to be lost megawatts in my opinion, but there will be shifting timelines as individual projects are resolved,” he said.
In New South Wales, an August data center framework ties faster assessment to development standards covering environmental performance, additional energy and water supply, community infrastructure, and skills. Qualifying projects receive a commitment to assessment within 75 days.
That process can accelerate planning decisions, but developers still need the infrastructure required to bring facilities online.
Power Connections Will Decide What Opens
Melbourne moved 1.2 GW into committed capacity during the reporting period, compared with 0.7 GW in Sydney. Tan said Victoria’s Development Facilitation Pathway helped eligible projects advance, while JLL’s Lee pointed to AI demand as another driver behind Melbourne’s growth.
National committed capacity increased from 3.1 GW to 5.2 GW. Melbourne’s early-stage capacity, however, rose by a more modest 0.3 GW to 7.8 GW, leaving most of its pipeline subject to significant delivery uncertainty.
DC Byte’s “committed” category signals confidence in eventual delivery based on secured development requirements or an operator’s track record. It does not establish when every phase will open.
Dr. William Lee, senior research director for computing systems platforms and technologies, enterprise infrastructure, at IDC, said developers need evidence beyond a project’s classification.
“An energization date, upstream transmission, and community consent will get them from ‘committed’ capacity to an opening date,” he told Data Center Knowledge. That assessment should include a signed connection agreement, schedules for transmission or terminal-station works, equipment delivery slots, and consent for network construction.
Victoria’s earlier planning advantage may also be subject to new uncertainty. DC Byte’s report pointed to new state policies and an apparent pause in approvals ahead of the November election as developments that could affect future forecasts.
Sydney and Melbourne Still Dominate the 2030 Outlook
DC Byte forecasts 3.9 GW of operational capacity by 2030, with Sydney and Melbourne accounting for about 3.4 GW. Despite regional expansion, the two established hubs remain central to near-term delivery.
The national forecast rises from 1.8 GW at the end of 2026 to 2.3 GW in 2027, 2.7 GW in 2028, 3.4 GW in 2029, and 3.9 GW in 2030. Sydney is projected to reach 2.0 GW by 2030, ahead of Melbourne’s 1.4 GW despite Melbourne’s larger development pipeline.
“The 3.9 GW is our forecast of fitted-out IT capacity available for use by 2030,” Tan said.
The forecast accounts for delivery likelihood, construction timelines, and phased openings, including historical patterns in how sold capacity is brought into operation.
IDC’s Dr. Lee said the target is achievable, but he identified local connection works for large campuses in Western Sydney and Melbourne’s west as the largest risk to delivery.
“Australia’s challenge before 2030 is connecting individual sites, not generating enough electricity,” he said.
“Australia’s challenge before 2030 is connecting individual sites, not generating enough electricity.” – Dr. William Lee, senior research director for computing systems platforms and technologies, enterprise infrastructure, IDC
JLL’s Lee also cited proposed terminal stations supporting large connections as a major delivery risk. Delays to those projects could hold back capacity even where customers are ready to occupy it.
Customer commitments cover about 90% of operational and under-construction capacity, according to Tan. That measure applies to the more advanced portion of the market rather than the full 26.8 GW national total.
Lee said he expected a high proportion of capacity arriving in 2027 and 2028 to be pre-committed, though larger supply additions from 2029 could begin to change that balance.
Regional Growth Faces Infrastructure and Staffing Limits
Locations outside Sydney and Melbourne now account for 31% of the pipeline, up from 19% two years ago. Tan highlighted growing interest around Morwell, east of Melbourne, as well as Western Australia and Queensland.
Regional New South Wales added 1.3 GW of early-stage capacity, while regional Victoria added 0.7 GW. The broader footprint also includes early-stage projects in Queensland, Tasmania, South Australia, and Western Australia.
“There is little doubt that large-scale power availability in metropolitan Melbourne and Sydney has an end date of some sort,” JLL’s Lee said.
Regional markets offer more choices for land and infrastructure, but connectivity, construction logistics, supply chains, and staffing remain less proven at large scale, he cautioned.
IDC’s Dr. Lee said credible regional sites need access to high-voltage infrastructure, renewable generation, a signed connection, and a water plan. Few locations currently combine all of those requirements for large deployments.
Australia’s relatively high costs also limit the workloads it can attract. JLL’s Lee said security considerations have supported demand across a range of workloads, but cost and development timelines can still favor other Asia-Pacific markets.
Dr. Lee argued that Australia’s strongest case lies in domestic demand and workloads that benefit from its regulatory environment and renewable resources.
“Australia should not chase after cost-led AI training capacity or overflow from Singapore,” he said. “It should base its demand case on domestic absorption like hyperscale cloud, sovereign and regulated workloads, AI inference, and flexible compute at renewable hubs.”