哈佛研究:403座美国数据中心年排放2570万吨CO2
情报详报
What happened A Harvard-led study published Nov. 16 in Nature Sustainability estimated the carbon footprint of 403 US hyperscale data centers operating from May 2024 through April 2025. The research, covered by Data Center Knowledge on Nov. 23, 2026, attributes an estimated 25.7 million metric tons of CO2 to electricity consumed at those facilities, with emissions largely determined by the regional power grids serving them. Lead author Gianluca Guidi, a Harvard scientist, said AI is rapidly increasing demand for computing infrastructure and creating substantial new electricity demand. The study covers both general-purpose computing and AI workloads and estimates electricity use through facility-load scenarios, assigning emissions based on regional generation data. Virginia, Oregon, Ohio, and Iowa accounted for more than half of the analyzed electricity consumption. Industry analysts and consultants quoted in the article discussed how power procurement, grid conditions, build timelines, and market-based versus location-based emissions accounting shape data center environmental footprints. ### Key figures - 403 US hyperscale data centers studied - 25.7 million metric tons of CO2 associated with one year of electricity use (central estimate) - 82 TWh central estimate of electricity consumption, about 1.8% of total US electricity use - Roughly 54% of electricity serving the studied sites generated from fossil fuels - Study period: May 2024 through April 2025; published Nov. 16 in Nature Sustainability - Scenario range for consumption: 68 TWh to 99 TWh - Scenario range for emissions: 21 million to 31 million metric tons of CO2 - Virginia, Oregon, Ohio, and Iowa: more than half of analyzed electricity consumption - IDC analyst expectation: US data center emissions to more than double by 2030 - Demand expected to outpace clean supply through at least 2028 (IDC) - A data center built today could influence electricity infrastructure decisions for 30 to 40 years (Guidi) ### Why it matters to ebm-papst This study reinforces that data center emissions are increasingly judged on power procurement and grid mix, not only on facility efficiency. For ebm-papst, that shifts the customer conversation toward total thermal and airflow efficiency per workload, because operators facing rising emissions scrutiny will look to reduce energy use in cooling and air movement even as total compute demand grows. The concentration of load in Virginia, Oregon, Ohio, and Iowa signals where hyperscale cooling demand and retrofit activity are likely to cluster. Analysts quoted expect demand to outpace clean supply through at least 2028 and emissions to more than double by 2030, which suggests continued pressure on operators to demonstrate efficiency gains and flexible operation. Assessment (inference): ebm-papst's opportunity is less about a single product claim and more about positioning high-efficiency fans and intelligent airflow control as measurable contributors to power-constrained campus design. Assessment (inference): the study's emphasis on regional grid constraints could favor suppliers who can support carbon-aware scheduling and demand-flexible cooling, turning fan efficiency into a procurement differentiator rather than a commodity specification. Assessment (inference): the article does not mention ebm-papst or any specific competitor, so no direct competitive threat can be inferred from the text.
原文全文
Study Ties 403 US Data Centers to 25.7M Metric Tons of CO2
A Harvard-led study found that 403 US hyperscale data centers were tied to 25.7 million metric tons of CO2, with emissions largely driven by regional power grids.
Electricity used at 403 US hyperscale data centers was associated with an estimated 25.7 million metric tons of carbon dioxide emissions over one year, underscoring how the power available to expanding campuses is shaping their environmental footprint.
The Harvard-led study, published Nov. 16 in Nature Sustainability, examined facilities operating from May 2024 through April 2025. Its central estimate put electricity consumption at 82 TWh, or about 1.8% of total US electricity use, with roughly 54% of the electricity serving those sites generated from fossil fuels.
Gianluca Guidi, a Harvard scientist and lead author of the study, said AI is rapidly increasing demand for computing infrastructure, creating substantial new electricity demand in the process.
“The climate consequences depend on how quickly the electricity system can respond with low-carbon generation,” he told Data Center Knowledge. “The environmental footprint of AI isn’t determined by the technology alone. It’s also determined by the energy systems we choose to build around it.”
For developers racing to bring capacity online, the findings put power procurement and grid conditions alongside building efficiency as key determinants of emissions. Faster computing and improved cooling can reduce energy use per workload even as total demand continues to rise.
Dan Versace, research analyst for environmental, social, and governance business services at IDC, told Data Center Knowledge he expected US data center emissions to more than double by 2030 as computing demand grows faster than clean electricity supply.
“It comes down to three things: how fast the load arrives, whether clean power is available where and when it’s needed, and whether efficiency gains get absorbed by growth,” Versace said.
Regional Grid Mix Drives Data Center Emissions
The report estimates electricity use through facility-load scenarios and assigns emissions based on regional generation data. Across those scenarios, consumption ranged from 68 TWh to 99 TWh, while associated emissions ranged from 21 million to 31 million metric tons of carbon dioxide.
Those estimates cover the facilities studied, not the entire US hyperscale market. The research also includes both general-purpose computing and AI workloads.
Virginia, Oregon, Ohio, and Iowa accounted for more than half of the electricity consumption analyzed, according to Harvard’s summary. That concentration makes regional energy infrastructure particularly consequential for future expansion.
Guidi said the longer-term concern is clear: a data center built today could influence electricity infrastructure decisions for the next 30 to 40 years.
“We should be careful not to address a rapidly growing technological demand by locking ourselves into decades of additional fossil-fuel dependence,” he cautioned.
“We should be careful not to address a rapidly growing technological demand by locking ourselves into decades of additional fossil-fuel dependence." – Gianluca Guidi, Harvard Postdoctoral Research Fellow
Gordon Johnson, senior CFD manager at Subzero Engineering, said the source of incremental electricity will determine whether rising demand translates into higher emissions.
“If the additional electricity needed comes from renewable or low-carbon sources, the emissions impact can be limited,” Johnson said. “If it comes from fossil-fuel generation, carbon emissions will increase.”
James Rogers Jones, head of sustainability development at BCS Consultancy, said procurement-based emissions reporting can differ substantially from the accounting used for local climate targets.
“Operators report low or net zero emissions using PPAs [power purchase agreements] and certificates (market-based),” he said. “County or city targets look at the actual local grid mix (location-based).”
Those differing accounting approaches can complicate planning discussions when a developer’s renewable energy claims sit alongside rising emissions attributed to local electricity demand.
Tight Build Timelines Push Developers Toward Available Power
Clean power projects and grid upgrades must come online on timelines that align with new campus openings. When they do not, developers may have to choose from whatever generation options are available when facilities begin operating.
Katherine Otway, chief strategy officer at nonprofit incubator and accelerator The Engine, said those competing timelines are increasingly shaping operators’ power choices.
“A developer may already have an opening date while a startup developing a new power system is still proving its technology,” Otway explained.
Otway added that some developers are turning to on-site gas turbines to meet opening schedules. For alternative technologies, commercial readiness depends not only on technical performance, but also on manufacturing, installation, and reliable operation.
Where new generation is built also matters, Johnson said, particularly for communities near power plants or in areas that may need additional generation capacity and could face higher air pollution.
Rising AI Demand Erodes Efficiency Gains
Jones said growing compute demand is absorbing many of the gains from efficiency improvements. He pointed to flexible electricity consumption, such as reducing load during peak demand or periods of low renewable output, as one way to better accommodate wind and solar.
Still, he cautioned, providing reliable power while preserving that flexibility remains a challenge for large sites.
Versace said operators can already deploy measures such as power capping, carbon-aware scheduling, and improved cooling. But their effect on overall emissions will depend on how quickly capacity expands and how much cleaner electricity becomes available.
“Demand will outpace clean supply through at least 2028,” he said. “That’s not a failure of clean energy so much as a reflection of how quickly this load is growing.”
Guidi said efficiency is essential, but it will not necessarily reduce total consumption if demand continues to grow even faster. More efficient chips, he noted, can enable more computation rather than simply reducing electricity use.
“We need additional clean generation, storage, transmission, smarter facility operation, and much better coordination between data center developers and electricity planners,” Guidi said. “The question isn’t simply whether we can build enough computing power. It’s whether we can build the energy infrastructure to support it responsibly.”