阳光电源参与Hams Hall储能项目,并网后20天进入商运,BW ESS称其为欧洲最大在运BESS
情报详报
What happened On 2 November 2026, BW ESS announced that the first phase of its Hams Hall battery energy storage project in the West Midlands, UK, had entered commercial operation at 350MW/1,243MWh. The site sits adjacent to National Grid's Hams Hall substation. In its announcement, BW ESS described the facility as the largest operating BESS in Europe by stored energy (MWh) — a company ranking statement rather than a unified ranking by an independent body. The transition from energisation/grid connection to commercial operation took 20 days, according to BW ESS and Sungrow announcements. The two companies use slightly different starting terminology — BW ESS refers to "energisation", while Sungrow refers to "grid connection" — though both point to the final post-connection stage. Neither company disclosed precise start dates or a day-by-day commissioning schedule. The project was not built from scratch within those 20 days. BW Group disclosed in May 2022 that the project had obtained full planning permission; BW ESS's project page lists construction starting in October 2024, while contractor Wills Bros records a construction period from July 2024 to April 2026. The public start-date references differ, but all indicate that the 20 days cover only the grid-connection-to-commercial-operation segment, not the overall construction period. Hams Hall uses Sungrow's PowerTitan 2.0 energy storage system and EMS3000 energy management system. Sungrow attributed the rapid commissioning to several on-site arrangements: BESS engineers stationed directly on site; prioritising fault identification and chiller operation checks during warm commissioning; OT engineers supporting system integration and troubleshooting during hot commissioning; and near-daily attendance by the BW ESS team with escalation channels to Sungrow headquarters. This is the supplier's account of the project process, not an independent third-party commissioning audit. BW ESS said first-phase long-term revenue is supported by a ten-year floor and optimisation agreement with EDF, which will optimise battery operation via its PowerShift platform. The public announcement did not disclose contract prices, guaranteed revenue amounts or actual operating returns. The next phase is planned to raise total site capacity to 400MW/1,424MWh, but no second-phase commissioning date was given. BW ESS estimates the full-scale project could support around 1.3 million households for up to 3.5 hours — a company conversion of full-scale capability, not an actual supply record. ### Key figures - First-phase capacity: 350MW/1,243MWh - Time from energisation/grid connection to commercial operation: 20 days - Full-site planned capacity: 400MW/1,424MWh - Full-scale duration estimate: up to 3.5 hours - Full-scale household-equivalent estimate: around 1.3 million households (company estimate) - EDF agreement term: 10 years (floor and optimisation agreement) - Full planning permission disclosed: May 2022 - Construction start: October 2024 (BW ESS project page) / July 2024 (Wills Bros record) - Construction period per Wills Bros: July 2024 to April 2026 - Contract prices, guaranteed revenue amounts and actual operating returns: not disclosed - Second-phase commissioning date: not disclosed ### Why it matters to ebm-papst Hams Hall is a large, high-profile reference for Sungrow's PowerTitan 2.0 and EMS3000 in a major European market, and the 20-day commissioning claim strengthens Sungrow's positioning on delivery speed and on-site engineering support — dimensions that matter to EPCs and developers choosing storage partners in the UK and wider Europe. Assessment (inference): For ebm-papst, the direct competitive threat is limited, since the company does not supply grid-scale battery systems. The more relevant signal is demand-side: a 350MW/1,243MWh BESS entering commercial operation, with expansion to 400MW/1,424MWh planned, implies sustained requirements for thermal management — cooling fans and blowers for containerised battery systems, HVAC for auxiliary enclosures, and possibly cooling for power conversion equipment. Assessment (inference): Sungrow's choice of cooling architecture for PowerTitan 2.0 in this project is not disclosed in the source, so it is uncertain whether ebm-papst content is present; the item should be treated as a market-signal lead rather than a confirmed account. Assessment (inference): The EDF optimisation agreement and the ten-year floor indicate the project is structured for long-term merchant-plus-contract operation, which supports aftermarket and service demand for cooling components over the asset lifetime. Assessment (inference): The rapid commissioning narrative also raises the bar on supplier responsiveness; if ebm-papst engages with UK BESS developers or with Sungrow's integration partners, fast on-site support and spare-part availability may become a differentiator in supplier selection.
原文全文
原文
英文翻译
(来源:储能世界)
“
20天,Hams Hall一期储能系统完成从并网/送电到商业运营的转换。规划、建设和并网准备工作在此前已持续推进多年。
2026年11月2日,BW ESS宣布,英国West Midlands地区的Hams Hall电池储能项目首期已进入商业运营,规模为350MW/1,243MWh。项目紧邻National Grid的Hams Hall变电站。BW ESS在公告中称,按储能量(MWh)计,这是欧洲最大在运BESS;这是一项公司排名表述,不是独立机构的统一排名。〔BW ESS公告〕
图:用户提供的储能设施航拍素材。
01
20天的计时起点与项目工期
02
调试提速背后的现场协同
03
商运安排与后续合作状态
01
TIMELINE
20天,计时从哪一步开始
BW ESS的公告写的是,项目在energisation(送电)后20天进入商业运营;Sungrow的公告则称,从grid connection(接入电网)到commercial operation(商业运营)用了20天。两种说法都指向并网后的最后阶段,但起点术语并不完全相同。两家公司没有公开精确的起始日期和逐日调试表,因此不宜把这20天拆成未经披露的工序天数。〔BW ESS公告,Sungrow公告〕
项目本身并非在这20天里从零建起。BW Group在2022年5月披露项目取得完整规划许可;BW ESS项目页列出2024年10月开工,承包商Wills Bros则将施工期列为2024年7月至2026年4月。公开页面的开工口径有差异,但共同说明:20天只对应并网/送电至商运这一段,不是项目的整体建设周期。〔规划许可公告,BW ESS项目页,Wills Bros项目记录〕
02
COMMISSIONING
驻场工程师,把调试问题留在现场解决
Hams Hall采用Sungrow的PowerTitan 2.0储能系统和EMS3000能量管理系统。Sungrow将快速推进归因于几项现场安排:BESS工程师直接驻场;warm commissioning阶段优先识别故障、检查冷却器运行;hot commissioning期间安排OT工程师支持系统集成和故障排除;BW ESS团队几乎每天到场,并与Sungrow总部保持升级沟通渠道。这是供应商对项目过程的说明,并非独立第三方的调试审计。〔Sungrow项目公告〕
图:用户提供的PowerTitan 2.0产品画面。画面规格属于产品展示信息,不代表Hams Hall项目逐台设备配置。
接下来的三张画面也来自用户提供的Sungrow产品演示素材。画面中关于系统效率、放电能力和提前预警的数字均为厂商产品资料口径,不能当作Hams Hall的现场实测结果。
图:Sungrow产品对比演示画面。
图:Sungrow产品系统结构与效率演示画面。
图:Sungrow 6D监测与预警演示画面;其中“提前24小时”是厂商产品说明,不是Hams Hall运行数据。
03
REVENUE
商运之后,收入安排与扩建仍有后续
BW ESS称,首期长期收入由与EDF签订的十年floor及优化协议提供支撑,EDF将通过PowerShift平台优化电池运行。公开公告没有披露合同价格、保底收入金额或实际运营收益。〔BW ESS与EDF协议公告〕
下一阶段计划把全场规模提高至400MW/1,424MWh,但现有公告没有给出二期投运日期。BW ESS估算,项目满规模后可支撑约130万户家庭用电、最长3.5小时;这是公司对满规模能力的换算,不是已发生的供电记录。〔BW ESS公告〕
04
PARTNERS
Sungrow其他合作项目,状态各不相同
Hams Hall之外,Sungrow还披露了几项不同阶段的合作。沙特7.8GWh储能项目由Najran、Khamis Mushait和Madaya三个站点组成,Sungrow称项目已于2025年接网,并为项目生产交付了1,500多套PowerTitan 2.0。〔Sungrow沙特项目公告〕
与Delta Capacity的1GWh协议是PowerTitan 2.0框架协议,公告计划在2026年内交付部署;与罗马尼亚ENEVO Group的1GWh合作则分为阶段推进,其中440MWh在2026年初已下单,另560MWh列为后续阶段。两项合作都不能直接表述为全部容量已经建成或投运。〔Delta Capacity框架协议,ENEVO合作公告〕
∞