# JLL forecasts US tender prices up 4.2% in 2027 as Southern data center labor shortages strain schedules

- Source: Data Center Knowledge (T2)
- Published: 2026-11-13
- Score: 33.4
- Tags: Market data, Datacenter
- Original: https://www.datacenterknowledge.com/data-center-construction/labor-shortages-threaten-data-center-schedules

## Intelligence brief

### What happened JLL, in its 2027 US Construction Perspective, forecasts that national construction tender prices — the amounts contractors bid for projects — will rise 4.2% in 2027, up from 3.1% in 2026 and above the pre-2020 norm of 2% to 3%. The projection covers the broader construction market, not data centers alone. The report was reported by Data Center Knowledge on November 13, 2026. According to JLL, data center developers face higher construction bids and intensifying competition for specialized workers in 2027, as demand for facilities and power infrastructure concentrates in Southern US markets where workforce capacity is already strained. The South is expected to contribute more to nonresidential construction growth than any other US region and to carry the heaviest workload per worker by 2028, driven by data centers, power projects, and public civil works. Matthew Giddings, JLL's executive director of technical services, told Data Center Knowledge that developers risk underestimating the cost of assembling qualified crews. "The challenge isn't just finding workers. It's finding qualified workers in the right location at the right time," he said, adding that the budget impact extends well beyond wage rates. Developers are paying overtime and covering travel, lodging, and relocation premiums to bring specialists into markets without sufficient local labor, but adding crews can also raise costs without improving productivity if designs, materials, and construction sequencing are not well coordinated. JLL said emerging data center markets may lack the workforce capacity to support multiple hyperscale developments simultaneously. Campuses increasingly include substations, utility infrastructure, and dedicated generation, requiring thousands of workers over multiyear construction programs. Giddings said workforce planning needs to happen alongside site selection, permitting, and utility strategy, and that early relationships with trade schools, community colleges, and apprenticeship programs can help build local capacity. Power delivery presents a related staffing challenge: utilities need crews for transmission lines and substations, while developers need electrical trades to build and energize facilities, and those labor pools are not interchangeable. Giddings cited situations where facilities were substantially complete with power available but remained months from operation because qualified commissioning personnel were unavailable. He urged developers to coordinate utility work, equipment procurement, construction, and commissioning within a single schedule. JLL identifies metals, energy-intensive products, and related building packages as sources of cost pressure. Tender prices typically trail input costs by three to six months, meaning increases through late 2026 will continue to affect bids in early 2027. Contractors also price in risks they cannot confidently assess, and established data center contractors with substantial backlogs can afford to be selective. Prefabricated electrical assemblies and standardized cooling infrastructure can reduce on-site labor requirements, but manufacturers still face staffing and capacity constraints; Giddings said repeatable designs deployed across campuses tend to add more value than isolated prefabrication decisions. ### Key figures - National tender price forecast: +4.2% in 2027, versus +3.1% in 2026 and a pre-2020 norm of 2% to 3% (broader construction market, not data centers alone). - Tender prices typically trail input costs by three to six months. - The South is expected to carry the heaviest workload per worker by 2028. - Multiyear data center campuses require thousands of workers. - No specific figures disclosed on data center construction cost inflation, labor wage premiums, or per-project staffing shortfalls. ### Why it matters to ebm-papst Higher tender prices and scarce specialized crews in Southern US data center markets affect the timing and cost of the facilities that drive demand for cooling fans and air-movement equipment. If construction schedules slip, equipment orders and delivery windows may shift accordingly, and developers under schedule pressure may favor standardized, prefabricated cooling infrastructure that reduces on-site labor. Assessment (inference): ebm-papst's opportunity lies less in construction labor itself than in positioning factory-assembled, standardized cooling and air-movement modules as a way to cut on-site electrical and mechanical labor hours, which are the constrained resource. Assessment (inference): the explicit warning that manufacturers of prefabricated assemblies face their own staffing and capacity constraints suggests that suppliers able to demonstrate reliable capacity and lead times will be favored over those competing on price alone. Assessment (inference): the emphasis on commissioning personnel as a bottleneck implies that equipment requiring less specialized on-site commissioning — and supported by remote diagnostics or factory-tested controls — could shorten time-to-operation and strengthen the supplier's value proposition with hyperscale developers and their contractors.

## Full text (original)

Labor Shortages Threaten Data Center Schedules
Labor shortages and rising costs are making data center schedules more fragile, especially in Southern markets where specialized crews are already stretched.
Data center developers face higher construction bids and intensifying competition for specialized workers in 2027, as demand for facilities and power infrastructure concentrates in Southern US markets where workforce capacity is already strained, according to JLL.
In its 2027 US Construction Perspective, JLL forecasts national tender prices – what contractors bid for projects – will rise 4.2% in 2027, up from 3.1% in 2026 and above the pre-2020 norm of 2% to 3%. The projection applies to the broader construction market rather than data centers alone.
The South is expected to contribute more to nonresidential construction growth than any other US region and to carry the heaviest workload per worker by 2028, driven by data centers, power projects, and public civil works.
Matthew Giddings, JLL’s executive director of technical services, told Data Center Knowledge that developers risk underestimating the cost of assembling qualified crews.
“The challenge isn't just finding workers. It's finding qualified workers in the right location at the right time,” he said. “The budget impact extends well beyond wage rates.”
Developers are paying overtime and covering travel, lodging, and relocation premiums to bring specialists into markets without sufficient local labor. But adding crews can also increase costs without improving productivity if designs, materials, and construction sequencing are not well coordinated, Giddings noted.
Labor Planning Must Start with Site and Power Strategy
JLL said emerging data center markets may lack the workforce capacity to support multiple hyperscale developments simultaneously. Campuses increasingly include substations, utility infrastructure, and dedicated generation, requiring thousands of workers over multiyear construction programs.
“You can't assume that labor will simply be available once a project is ready to break ground,” Giddings said. “Workforce planning needs to happen alongside site selection, permitting, and utility strategy.”
He added that early relationships with trade schools, community colleges, and apprenticeship programs can help build local capacity, while waiting until construction is near leaves developers competing for workers already committed elsewhere.
Power delivery presents a related staffing challenge. Utilities need crews for transmission lines and substations, while developers need electrical trades to build and energize facilities. Those labor pools are not interchangeable, Giddings said.
“We've seen situations where facilities were substantially complete with power available but remained months away from operation because qualified commissioning personnel weren’t available,” he said.
To reduce that risk, Giddings urged developers to coordinate utility work, equipment procurement, construction, and commissioning within a single schedule.
Project Uncertainty Is Driving Bids Higher
JLL’s outlook identifies metals, energy-intensive products, and related building packages as sources of cost pressure. Tender prices typically trail input costs by three to six months, meaning increases through late 2026 will continue to affect bids in early 2027.
Giddings said contractors also price in risks they cannot confidently assess.
“When a contractor is asked to commit to a guaranteed price or delivery date before design is fully developed or procurement risks are understood, they're going to account for that uncertainty in their pricing,” he explained.
Early contractor involvement, clearer procurement plans, and an experienced owner’s team can improve pricing predictability. Established data center contractors with substantial backlogs can also afford to be selective, making it harder for owners to pass unresolved project risks downstream at low cost.
Prefabricated electrical assemblies and standardized cooling infrastructure can reduce on-site labor requirements, but manufacturers still face staffing and capacity constraints. Giddings said repeatable designs deployed across campuses tend to add more value than isolated prefabrication decisions.
Spending More Only Helps If It Removes the Bottleneck
For AI-focused campuses, earlier operation can justify substantial additional spending. Developers should weigh acceleration against financing costs, customer commitments, equipment deployment, and revenue lost through delayed occupancy, Giddings said.
That calculation depends on whether the additional spending actually changes the opening date. More construction labor offers little benefit if equipment delivery or commissioning still determines when the facility can operate.
“Adding overtime or manpower doesn't help if the true constraint is transformer delivery, utility energization, or commissioning,” Giddings said. “Successful acceleration strategies target the actual bottlenecks rather than simply increasing construction spend.”