# Samsung and SK hynix commit KRW 10–20tn each to lock ASML EUV capacity for 2027–2028 DRAM/HBM expansion

- Source: JW Insights (T2)
- Published: 2026-01-01
- Score: 21.4
- Tags: Market data, Cleanroom, Datacenter
- Original: https://www.laoyaoba.com/n/1138174

## Intelligence brief

### What happened Samsung Electronics and SK hynix are engaged in a delivery-slot contest for extreme ultraviolet (EUV) lithography tools from ASML, according to foreign media reports citing sources. Each company is committing a scale of KRW 10–20 trillion to secure scarce ASML capacity in 2027–2028, positioning themselves for expanded advanced DRAM and HBM output. ASML has already warned explicitly on its Q3 earnings call that even with EUV capacity raised 30% in 2027 and a further 30% in 2028, it will still be unable to meet customer demand. EUV shipments this year are around 65 units, up nearly 50% from 44 units last year, but the supply bottleneck persists: lead times for core equipment have stretched to twice the original level, and price increases are expected to surface in 2027 and become fully visible the following year. Memory customers accounted for 46% of ASML system sales in Q3 this year. SK hynix said in March this year that it would procure about KRW 11.95 trillion of EUV equipment, with delivery deadlines set for the end of 2027. As the 1c process (10nm-class sixth-generation DRAM) scales down, the number of EUV layers rises from three previously to more than five, pushing up per-line equipment demand. TrendForce notes that the more advanced the process, the more exposure hours and tool counts become a powerful constraint on capacity ramp-up. Samsung is placing orders in step with its Pyeongtaek P5 line, part of a five-year KRW 450 trillion domestic investment plan. A single fab there carries investment of more than KRW 60 trillion and targets production startup in 2028; the first-phase cleanroom is expected to be completed in the first half of next year, with lithography equipment moving in progressively. Samsung also plans to adopt High-NA EUV in 2028 to capture the advanced DRAM mass-production window. Equipment tightness is spreading from front-end to back-end. Advanced packaging houses such as Hanmi Semiconductor and Amkor have order visibility booked out two to three years, and demand is rising for HBM-critical process tools such as thermal compression bonders (TC bonders). Industry figures read this as AI data-center chips competing not only on front-end process but also on back-end multi-dimensional stacking and interconnect value, deepening the linkage between front- and back-end prosperity. Analysts say the essence of this round of orders is buying time: whoever locks tools first and completes validation can pull ahead in the HBM and next-generation DRAM cycle; conversely, rising capex, depreciation and capital-occupation pressure will also grow. ### Key figures - Per-company commitment: KRW 10–20 trillion each (Samsung, SK hynix) - Target capacity window: ASML EUV tools for 2027–2028 - ASML EUV capacity growth plan: +30% in 2027, a further +30% in 2028, still insufficient to meet demand - ASML EUV shipments: about 65 units this year vs 44 units last year (up nearly 50%) - Equipment lead times: stretched to twice the original level - Price increases: expected to surface in 2027, fully visible in 2028 - Memory share of ASML system sales: 46% in Q3 this year - SK hynix EUV procurement: about KRW 11.95 trillion, delivery by end-2027 - EUV layers per DRAM line: from 3 to more than 5 as 1c process scales - Samsung P5: part of a five-year KRW 450 trillion domestic investment plan; single fab over KRW 60 trillion; production target 2028; first-phase cleanroom completion in H1 next year - Samsung High-NA EUV adoption: planned for 2028 - Advanced packaging order visibility: two to three years ### Why it matters to ebm-papst Memory fabs of this scale imply large cleanroom and process-cooling build-outs: P5's first-phase cleanroom completion in H1 next year and progressive tool move-in mean ventilation, air-handling and cooling demand at the construction stage precedes the 2028 production start. The front-end expansion is matched by back-end packaging capacity additions (Amkor, Hanmi Semiconductor) with two-to-three-year order visibility, another cleanroom-intensive segment. Assessment (inference): The EUV tool bottleneck does not directly touch ebm-papst, but the capex it triggers does — fab construction schedules at Pyeongtaek and packaging lines are addressable demand for cleanroom air movement and cooling solutions, and the 2027–2028 tool delivery timeline gives a rough window for when facility HVAC and process cooling specifications get locked. Assessment (inference): Korean memory makers' capex concentration also raises competitive intensity among fan and cooling suppliers bidding on these projects, so early engagement with fab engineering and EPC contractors matters more than price positioning. Assessment (inference): The stated shift of value toward back-end stacking suggests packaging cleanrooms deserve equal attention to front-end fabs in the addressable pipeline.

## Full text (English translation)

13 minutes ago — The lithography battle begins: Samsung and others spend heavily to compete for EUV capacity, stepping up advanced DRAM expansion.

South Korea's Samsung Electronics and SK hynix are engaged in a "delivery-schedule contest" over extreme ultraviolet (EUV) lithography machines. Foreign media, citing sources, reported in the latest update that the two are each committing a scale of between KRW 10 trillion and KRW 20 trillion, with the goal of locking in ASML's scarce 2027–2028 capacity and securing positions for advanced DRAM and HBM expansion.

ASML has already explicitly warned on its Q3 earnings call: even if EUV capacity is raised 30% in 2027 and expanded a further 30% in 2028, it will still be unable to meet customer demand. EUV shipments this year are about 65 units, up nearly 50% from 44 units last year, but the supply bottleneck continues to intensify; lead times for core equipment have stretched to twice the original level, and price increases are expected to surface in 2027 and become fully visible the year after next. In Q3 this year, memory customers already accounted for 46% of ASML's total system sales.

SK hynix said in March this year that it would purchase about KRW 11.95 trillion of EUV equipment, with delivery deadlines set for the end of 2027. As the 1c process (10nm-class sixth-generation DRAM) scales down, the number of EUV layers applied rises from three in the past to more than five, and per-line equipment demand climbs in tandem. TrendForce points out that the more advanced the process, the more exposure hours and machine counts become a powerful constraint on capacity ramp-up.

Samsung, for its part, is placing orders in step with the rhythm of its Pyeongtaek P5 line. That fab belongs to a five-year KRW 450 trillion domestic investment plan; a single wafer fab there involves investment of more than KRW 60 trillion and targets production startup in 2028; the first-phase cleanroom is expected to be completed in the first half of next year, with lithography equipment moving in progressively. Samsung also plans to introduce High-NA EUV in 2028 to seize the advanced DRAM mass-production window.

Equipment shortages are extending from the front-end to the back-end. Advanced packaging plants such as Hanmi Semiconductor and Amkor already have order visibility booked out two to three years, and demand for HBM-critical process equipment such as thermal compression bonders (TC Bonder) is rising. Industry insiders read this as AI data-center chips competing not only on front-end process, but with back-end multi-dimensional stacking and interconnect value rising in parallel, and the prosperity of front- and back-end becoming more tightly bound.

Analysts point out that the essence of this round of orders is "buying time": whoever locks machines first and completes validation can pull ahead in the HBM and next-generation DRAM cycle; conversely, upward capital expenditure, depreciation and capital-occupation pressure will also increase in tandem.

## Full text (original)

韩国三星电子与SK海力士正围绕极紫外（EUV）光刻机展开一场「交付排期争夺战」，外媒引述消息人士最新报道指出，两者各自投入规模介于10万亿至20万亿韩元，目标是锁定ASML 2027至2028年稀缺产能，为先进DRAM与HBM扩产卡位。
ASML已在第三季财报会议明确示警：即便2027年EUV产能提升30%、2028年再扩产30%，仍无法满足客户需求。今年EUV出货量约65台，较去年44台增长近50%，但供给瓶颈持续发酵；核心设备交付周期已拉长至原水准两倍，涨价效应预计2027年浮现、后年充分显现，今年Q3存储器客户占ASML整机销售比重已达46%。
SK海力士今年3月曾说，采购约11.95万亿韩元EUV设备，交付期限订于2027年底。随着1c制程（10纳米级第六代DRAM）微缩，EUV应用层数由过去3层增加至5层以上，单线设备需求同步攀升。
集邦咨询（TrendForce）指出，制程越先进，曝光工时与机台数量越成为产能爬坡的强大束缚。
三星则配合平泽P5产线节奏下单。该厂隶属五年450万亿韩元本土投资方案，单座晶圆厂投资逾60万亿韩元，目标2028年投产；一期无尘室预计明年上半年完工，光刻设备将陆续进场。三星同时规划2028年导入High-NA EUV，抢下先进DRAM量产窗口。
设备紧缺正从前道延伸至后道。韩美半导体、安靠（Amkor）等先进封装厂订单能见度已排满两至三年，热压键合机（TC Bonder）等HBM关键制程设备需求走扬。
业内人士判读，AI数据中心芯片不只比前段制程，后端多维度堆叠互连价值同步抬升，前后段景气绑定加深。
分析人士指出，这轮抢单本质是「抢时间」：谁先锁定机台、完成验证，谁就能在HBM与下一代DRAM周期拉开身位；反之，资本开支上行、折旧与资金占用压力也将同步放大。