# Vertiv and NVIDIA launch pre-engineered AI factory model claiming 30% more token output in 12 months

- Source: News · Vertiv (T2)
- Published: 2026-11-03
- Score: 73.2
- Tags: Datacenter, Product launch
- Companies: Vertiv, NVIDIA
- Original: https://digitalterminal.in/tech-companies/vertiv-and-nvidia-unveil-ai-factory-approach-to-boost-token-output-by-up-to-30

## Intelligence brief

### What happened At NVIDIA GTC Berlin, Vertiv and NVIDIA introduced a joint AI factory approach that pairs rapid configuration and virtual validation of pre-engineered reference architectures with factory-built deployment. The approach combines the NVIDIA Vera Rubin DSX AI Factory reference design and the NVIDIA Omniverse DSX Blueprint with Vertiv SimReady power and cooling assets, integrated through Dassault Systèmes' 3DEXPERIENCE agentic platform. Vertiv is also contributing SimReady OpenUSD assets of its power and cooling equipment to the SimReady Central Library on Hugging Face. The deployment side draws on Vertiv OneCore, a hybrid-built data center solution integrating critical power, thermal management and supporting infrastructure, and Vertiv SmartRun, a prefabricated overhead infrastructure system for high-density power distribution, liquid cooling, networking and containment. Polar Data Centers is applying the factory-built model to the first 41 MW phase of its multiphase AI data center at Herøya, Norway, a campus scalable to 100 MW; Vertiv is supplying prefabricated power and thermal modules, SmartRun overhead infrastructure and SmartMod, supported by Vertiv Unify software. Vertiv and NVIDIA plan to demonstrate elements of the approach at the show, with Dassault Systèmes technology and a Polar Data Centers real-world example. ### Key figures - Up to 30% more cumulative token output within the first 12 months at the same installed capacity, under defined assumptions (modeled scenario). - Configuration and virtual validation time reduced from approximately 30 days to three days, described as a 10x improvement (modeled scenario). - Infrastructure deployment period reduced from approximately 90 days to 45 days, a reduction of up to 50% (modeled scenario). - Combined configuration, validation and deployment reduced from approximately 120 days to 48 days, making productive AI capacity available about 10 weeks sooner (modeled scenario). - Polar Data Centers Herøya first phase: 41 MW, campus scalable to 100 MW. - No specific figures disclosed on contract value, Vertiv revenue contribution, or unit volumes. ### Why it matters to ebm-papst This is a competitive and channel signal in the AI data center cooling space. Vertiv is positioning pre-engineered, factory-built power and thermal infrastructure as the default delivery model for AI factories, tightly coupled to NVIDIA reference designs and validated in digital twins before construction. That raises the bar for component suppliers: fans and cooling components will increasingly need to be available as validated digital assets (SimReady/OpenUSD) that plug into Omniverse-based design workflows, not just as physical hardware specified late in the project. Assessment (inference): The 30% token-output claim is a commercial framing device that shifts buyer attention from capex per MW to time-to-revenue, which favors suppliers able to support prefabrication, standardized interfaces and early design integration. For ebm-papst, the near-term risk is that Vertiv's prefabricated thermal modules lock in incumbent fan and blower selections at the factory rather than at the site, reducing late-stage specification opportunities. The offsetting opportunity is on the liquid-cooling and high-density air-movement side, where prefabricated overhead systems such as SmartRun create repeatable, volume-based demand for standardized fan platforms. The Herøya 41 MW phase and the 100 MW scalability indicate a referenceable Nordic deployment that could shape European AI data center specifications. Assessment (inference): ebm-papst should evaluate whether its fan assets can be published as SimReady/OpenUSD digital twins for libraries such as SimReady Central Library on Hugging Face, since design-phase presence is becoming a precondition for factory-built specification. No statement from ebm-papst or any indication of its involvement appears in the source.

## Full text (original)

At NVIDIA GTC Berlin, Vertiv Holdings Co. and NVIDIA introduced an AI factory approach that combines rapid configuration and virtual validation of pre-engineered reference architectures with factory-built deployment. The approach is designed to move AI factories from project kickoff to productive capacity faster and, under defined assumptions, generate up to 30% more cumulative token output within the first 12 months with the same installed capacity. Polar Data Centers is applying the factory-built deployment approach to the first 41 MW phase of its multiphase AI data center at Herøya, Norway.
For AI factory operators, securing compute is only part of the challenge. Traditional infrastructure development can require power, cooling and facility systems to be engineered and integrated through separate, sequential processes, creating complexity and potential delays. The Vertiv and NVIDIA approach starts instead with pre-engineered AI factory reference architectures that can be rapidly configured to customer and site requirements, virtually validated before deployment, and then translated into factory-built infrastructure.
Configure and Validate: Up to 10x Faster with Pre-Engineered Reference Designs
Teams can start with pre-engineered AI factory reference designs and rapidly configure them for specific compute, power, cooling and facility requirements in a shared virtual environment. The approach combines the NVIDIA Vera Rubin DSX AI Factory reference design and NVIDIA Omniverse DSX Blueprint, with Vertiv SimReady power and cooling assets, integrated with Dassault Systèmes’ 3DEXPERIENCE agentic platform.
Rather than developing an integrated infrastructure design from scratch, teams can configure and virtually validate proven reference designs against project requirements, interfaces and constraints. In the modeled scenario, this reduces the time from requirements to a configured and validated AI factory solution from approximately 30 days to three days, a 10x improvement.
Vertiv is also contributing SimReady OpenUSD assets of its power and cooling equipment to SimReady Central Library on Hugging Face. The library helps engineering teams discover and reuse validated equipment assets in AI factory digital twins, reducing asset preparation and helping teams evaluate infrastructure options during design.
Deploy: Up to 50% Faster with Factory-Built Infrastructure
Once the AI factory configuration is validated, Vertiv prefabricated solutions shift more assembly, integration and testing into the factory before equipment reaches the site. These solutions include Vertiv™ OneCore, a hybrid-built data center solution that integrates critical power, thermal management and supporting infrastructure, and Vertiv™ SmartRun, a prefabricated overhead infrastructure system for high-density power distribution, liquid cooling, networking and containment.
By moving more infrastructure work off-site, teams can reduce field complexity and on-site integration requirements. In the modeled scenario, the factory-built approach reduces the infrastructure deployment period from approximately 90 days to 45 days, a reduction of up to 50%.
Combined with the faster configuration and validation enabled by pre-engineered reference designs, the modeled approach reduces these stages from approximately 120 days to 48 days. That can make productive AI capacity available about 10 weeks sooner, generating up to 30% more cumulative token output within 12 months of project kickoff with the same installed capacity.
Field Deployment: Polar Data Centers at Herøya, Norway
At its Herøya campus in Norway, Polar is using Vertiv's factory-built deployment model for the first 41 MW phase of its multiphase AI data center, scalable to 100 MW. By shifting more infrastructure assembly, integration and testing into the factory before equipment reaches the site, the deployment model is designed to reduce on-site complexity and help make high-density, liquid-cooled capacity available to customers sooner. Vertiv is supplying prefabricated power and thermal modules, Vertiv™ SmartRun overhead infrastructure and Vertiv™ SmartMod, supported by Vertiv™ Unify software.
“An AI factory earns its return in tokens, and every day spent configuring infrastructure or integrating it on site is output that never comes back,” said Giordano Albertazzi, CEO of Vertiv. “Success depends on how quickly operators can move from requirements to productive AI capacity. By starting with pre-engineered reference designs that can be rapidly configured and validated, then extending that approach through factory-built deployment, we help customers reduce complexity, deploy infrastructure faster and bring AI capacity online sooner. Polar Data Centers is demonstrating how that approach can be applied at scale in a real-world AI factory deployment.”
“AI factories must be designed as one system, and the NVIDIA Vera Rubin DSX AI Factory reference design helps teams align compute, power and cooling requirements from the outset,” said Vladimir Troy, vice president of AI infrastructure at NVIDIA. “With the NVIDIA Omniverse DSX Blueprint, companies such as Vertiv and Dassault Systèmes can simulate these systems together and carry an integrated design into physical deployment, helping operators resolve conflicts earlier and bring productive AI capacity online sooner.”
"With Vertiv and NVIDIA, we're accelerating AI factory design and deployment by engineering the factory as one system – compute, networking, power and cooling co-designed and co-simulated in a virtual twin,” said Stéphane Sireau, Vice President, High-Tech Industry, at Dassault Systèmes. “Integration issues get resolved before construction, not on site, helping bring token-producing capacity online sooner.”
“Our customers measure us on how quickly capacity is ready for them,” said Andy Hayes, CEO of Polar Data Centers. “At Herøya, Vertiv’s factory-built infrastructure helps us manage the complexity of deploying power, cooling and white-space systems for high-density computing. It gives us a more disciplined, repeatable deployment model while preserving the flexibility to meet the requirements of our customers.”
Vertiv and NVIDIA plan to demonstrate elements of the approach at NVIDIA GTC Berlin, including how facility requirements inform infrastructure configuration, how teams can virtually validate power and cooling requirements, and how Vertiv applies factory-built infrastructure to accelerate physical deployment. The demonstration will feature technology from Dassault Systèmes, and Polar Data Centers will show how the deployment approach is being applied in a real-world AI factory.