What happened Nanjing-based TICA (Nanjing TICA Environmental Technology Co., Ltd.) has completed what it describes as the world's largest cooling-capacity test platform for data-center refrigeration equipment, built at its Nanjing production base. The platform is designed to validate both air-cooled and liquid-cooled data-center cooling equipment at up to 3 MW of cooling capacity. Alongside the test platform, TICA has commissioned a new CDU (coolant distribution unit) manufacturing line, which is now running stably and assembling core cabinets in batch. A Class 100,000 cleanroom next to the line has been completed and is about to enter production. The facility is dedicated to high-capacity liquid-cooling systems for AI computing and data centers, with first products expected to be delivered to customers for testing and acceptance by the end of this month (November 2026, per the publication date). TICA says it has built a full-chain self-developed product system spanning primary-side cooling sources, secondary-side cooling sources and air-cooled terminals. Chen Xiaokang, manufacturing head at the TICA base, said manufacturing capability covers CDU products, liquid-cooling stainless steel piping and related accessories, with main product specifications ranging from 480 kW to 2 MW, which he characterized as internationally leading. The test platform has a maximum test cooling capacity of 850 refrigeration tons and covers a temperature range from -40°C to +60°C, enabling full-operating-condition performance validation and long-term reliability testing. Combined with TICA's existing 50-plus CNAS-accredited laboratories and a 600 kW data-center-dedicated laboratory, the company says it now has full-product, full-process performance and system reliability verification capability. Chen said the large platform serves two purposes: giving TICA's own laboratories complete validation of in-house products, and supporting a planned capacity expansion of 3 to 5 times, with future moves toward integrated prefabricated cooling solutions. ### Key figures - Test platform maximum cooling capacity: 3 MW (described as the world's largest for data-center air/liquid cooling testing) - Maximum test cooling capacity in refrigeration tons: 850 RT - Test temperature range: -40°C to +60°C - CDU main product specification range: 480 kW to 2 MW - Cleanroom class: Class 100,000 (ISO 8 equivalent) - Existing CNAS-accredited laboratories: more than 50 - Existing data-center-dedicated laboratory capacity: 600 kW - Planned capacity expansion: 3 to 5 times - First product delivery timing: by end of this month (November 2026, based on publication date) ### Why it matters to ebm-papst TICA is positioning itself as a vertically integrated supplier of liquid-cooling and air-cooling infrastructure for AI data centers, from primary cooling sources through CDUs to air-cooled terminals, backed by a test platform that lowers its own validation risk and shortens time-to-market. For ebm-papst, this is primarily a competitive and channel signal in the data-center cooling value chain: CDUs and liquid-cooling skids still require pumps, fans, heat exchangers and control electronics, and a supplier that builds its own full chain in-house may internalize more of that content or set stricter specification requirements for external components. Assessment (inference): TICA's stated 3-5x capacity expansion and its move toward integrated prefabricated cooling solutions suggest growing volume demand for air-moving and thermal-management components in the Chinese AI data-center market, which could represent a component supply opportunity for ebm-papst if it can qualify into TICA's platforms. Assessment (inference): conversely, TICA's emphasis on self-developed full-chain systems and internationally leading manufacturing capability signals an ambition to compete on complete cooling solutions rather than components, which raises the risk that Chinese OEMs bundle air-movement content in-house or source it from domestic suppliers, pressuring ebm-papst's position in this segment. Assessment (inference): the 850 RT / 3 MW test capability also raises the bar for validation evidence that component suppliers will be expected to provide, favoring vendors able to support full-operating-condition and long-term reliability testing.
原文全文
原文
英文翻译
AI产业持续升温,如何给大算力机房“降温”成为影响产业发展的关键之一。南京天加环境科技有限公司积极应对未来需求,成功构建了从一次侧冷源、二次侧冷源到风冷末端的全链条自研产品体系,并为其核心设备搭建了测试容量全球最大的“大冷量数据中心制冷装备综合测试平台”。
CDU号称液冷系统的“心脏枢纽”,负责把冷液精准输送到每一颗芯片。走进南京天加环境的生产车间,一条崭新的CDU智造产线已经在稳定运行,一台台核心机柜正在进行线上批量组装。生产线旁,一座十万级洁净室也已经搭建完毕,即将投入生产。这里生产的是面向未来的大冷量液冷系统,专门服务于人工智能算力和数据中心。预计本月底,首批产品就将交付客户进行测试和验收。
“我们现在的制造能力覆盖CDU产品、液冷不锈钢管路以及各类配套配件生产,主力产品规格从480千瓦延伸至2兆瓦,整体制造能力与产品水平处于国际领先。” 天加环境基地制造负责人陈小康说。
为验证该产品性能和质量,天加环境还建成了全球最大的3兆瓦数据中心风冷/液冷测试平台。该平台的最大测试冷量达850冷吨,测试能力覆盖零下40度到零上60度区间,可开展产品的全工况性能验证和长期可靠性检验。结合天加已有的50多座CNAS实验室与600千瓦数据中心专用实验室,天加环境已经具备了全产品、全流程的性能与系统可靠性验证能力,匹配全球数据中心制冷设备未来发展的方向。
陈小康介绍,搭建这套大型测试平台有两层考量。一方面,自有实验室可以为本企业自研产品提供完整验证;另一方面,企业后续产能计划扩大3至5倍,未来还将推进整套制冷方案集成预制相关布局。