友达中科两厂388亿新台币售予台积电,资产活化告一段落

AUO sells two Central Taiwan fabs to TSMC for NT$38.8bn, booking NT$18.5bn gain
集微网(半导体/面板 → 洁净室需求)T22026-01-01 · CN · 台积电 TSMC
产能建厂/搬迁/关停洁净室
▾ 1 条同事件报道

情报详报

What happened AUO chairman Paul Peng, speaking at the company's investor conference on 29 December, confirmed that AUO will sell its Central Taiwan (Taichung) L7 fab (a 7.5-generation line) and L5C fab (a 5th-generation line) to TSMC for NT$38.8 billion. The disposal is expected to generate a gain of roughly NT$18.5 billion. Peng said the transaction marks the end of AUO's asset-revitalization program. The sale follows an exclusive report by this newspaper in mid-August that AUO would sell the two Central Taiwan plants to TSMC for more than NT$30 billion; Peng confirmed the report at the conference. Separately, AUO's board had previously approved the disposal of the L3D and L5D plants in the Hwaya (Guishan, Taoyuan) campus to Quanta Computer for NT$19.7 billion. Because the two sides failed to reach consensus, AUO resolved on the same day to terminate that sale and will continue to look for suitable buyers. Quanta announced in parallel that the planned purchase of the two AUO Hwaya buildings had been cancelled because the parties could not agree on building specifications and handover timing. Quanta stressed that its AI server capacity plans are unaffected. Quanta had intended to use the two buildings for back-end assembly, testing and validation of AI servers, with handover targeted for the fourth quarter of 2027 to support AI product orders from 2028 onward. Quanta said no physical contract had been formally signed, so the failed deal has no financial impact. Peng said AUO's asset-revitalization work is now complete. The disposals are aimed at focusing on an asset-light operating model, revitalizing assets and optimizing the financial structure. Proceeds from future plant sales will be invested first in new businesses and new technologies, including MicroLED, optical communications, AI-related applications and advanced semiconductor packaging. On use of the funds, Peng said that in addition to new technology development and equipment for future mass production, AUO will use part of the proceeds to improve its financial structure and maintain a stable dividend policy. Regarding the sale of the Central Taiwan Phase 2 plant to TSMC, Peng said the site is still in production and that a production halt, handover and administrative procedures remain to be completed. The disposal gain will therefore not be recognized this year; whether it can be booked next year or the year after depends on the progress of those procedures. ### Key figures - Sale price of Central Taiwan L7 (7.5G) and L5C (5G) fabs to TSMC: NT$38.8 billion - Estimated disposal gain: approximately NT$18.5 billion - Earlier exclusive report (mid-August): sale value of more than NT$30 billion - Previously approved Hwaya L3D/L5D sale to Quanta: NT$19.7 billion (terminated) - Quanta handover target for the Hwaya buildings: Q4 2027, supporting orders from 2028 onward (deal cancelled) - Recognition of the TSMC disposal gain: not in the current year; timing for later years undetermined ### Why it matters to ebm-papst TSMC's acquisition of two AUO fabs in Central Taiwan signals continued expansion of its footprint in Taichung, where the company operates leading-edge capacity. Converting display fabs into semiconductor facilities implies cleanroom construction, tool installation and HVAC build-out, which is a demand signal for cleanroom ventilation, fan-filter units and precision air-movement equipment. AUO's stated intent to redeploy proceeds into advanced packaging, MicroLED and AI-related applications points to further cleanroom and process-cooling investment in Taiwan's display-to-semiconductor conversion wave. Assessment (inference): The terminated Quanta deal removes one near-term AI server assembly project in Hwaya, but Quanta says its capacity plans are unaffected, so the net effect on fan demand is likely a shift in location and timing rather than a reduction. Assessment (inference): ebm-papst should treat TSMC's Taichung build-out and AUO's advanced-packaging pivot as priority cleanroom accounts, while monitoring whether the Hwaya facilities find a new buyer that could revive a separate ventilation opportunity.

原文全文

原文 英文翻译
友达董事长彭双浪昨(29)日于法说会指出,将把旗下中科L7厂(7.5代厂)与L5C厂(5代厂),以388亿新台币售予台积电,预估处分利益约185亿新台币,友达活化资产作业也将在本案后告一段落。 本报8月中旬独家报道,友达将以逾300亿新台币出售中科二座厂予台积电,彭双浪昨天证实相关消息。不过,友达先前董事会通过将以197亿新台币处分华亚厂区内L3D厂 / L5D厂予广达案,因双方未达成共识,昨天决议终止出售案,未来将持续寻找合适买家。 广达昨天同步公告,原订购买友达华亚二座厂房案,因双方对厂房使用规格及交付时程未达成共识,因此撤销原约定交易。广达强调,相关AI服务器产能规划均不受影响。 广达原规划买进的两厂房将用于AI服务器后段组装、测试与验证,预计2027年第4季完成点交,进一步支应2028年后的AI产品订单需求。广达说明,由于双方未正式签订任何实体合约,因此此交易不成立不会对财务造成影响。 彭双浪并宣布,友达活化资产作业迄今,将告一段落。这次处分资产,主要为了聚焦轻资产营运模式、活化资产及优化财务结构。未来处分厂房回收的资金,将优先投入新事业与新技术,包括MicroLED、光通讯、AI相关应用及半导体先进封装等领域。 至于资金如何运用,彭双浪表示,除了投入新技术开发及未来量产所需设备外,友达也将运用部分资金改善财务结构,并维持稳定的股利政策。 谈到中科二期厂房卖给台积电,彭双浪说,该厂区目前仍持续生产中,后续还待完成停产、点交及行政程序,确定今年不会认列处分利益;至于明年或后年能否入账,尚待视相关程序进度而定。