What happened Infosys has published a new analysis of AI energy demand through 2030, concluding that data center operators facing power constraints can accommodate more AI computing by improving efficiency and shifting flexible workloads, but that such demand-side measures are unlikely to remove the need for new electricity infrastructure. The findings were reported by Data Center Knowledge on October 22, 2026, drawing on an interview with Mit Majumdar, executive vice president and global head of services for utilities, resources, and energy at Infosys. Majumdar told Data Center Knowledge that AI-driven energy management, advanced cooling, and peak-load optimization can create meaningful near-term headroom, though he did not provide a numerical estimate of the additional AI capacity these measures could support. He characterized the measures as more likely to delay rather than eliminate the need for new generation, transmission, and grid upgrades, and advocated a dual-track strategy: maximize existing capacity while accelerating investment in generation, transmission, and grid modernization. The analysis identifies a mismatch between AI adoption cycles measured in months and energy infrastructure development measured in years. It distinguishes flexible workloads — model training, retraining, and batch processing that can be scheduled around grid conditions — from real-time inference and customer-facing applications that generally cannot. Majumdar said facilities serving both categories cannot assume their entire AI load is available for curtailment, and that broader flexibility will require workload-aware service-level agreements, demand-response incentives, and pricing structures that reward customers for shifting non-urgent compute. On efficiency, the report recommends matching models to tasks and applying quantization, pruning, and knowledge distillation, plus measuring energy use and carbon emissions at the workload level. Majumdar urged developers to pursue staged, modular construction rather than locking in every project phase to current assumptions, to avoid both overbuilding and underestimating long-term demand. For utilities, he said projections alone are insufficient: they should require measurable and verifiable proof, including historical performance, real-time monitoring, and contractual commitments to reduce load when needed, with risk shared between operators and utilities. ### Key figures - Analysis horizon: AI energy demand through 2030. - No specific figures disclosed for additional AI capacity, capacity volumes, investment amounts, or market shares; Majumdar explicitly did not provide a numerical estimate of near-term headroom. - Qualitative timing contrast cited: AI adoption cycles measured in months versus energy infrastructure development measured in years. ### Why it matters to ebm-papst This analysis reinforces a market signal relevant to ebm-papst's data center cooling business: demand-side efficiency and peak-load optimization are being framed as near-term capacity levers, which elevates the value of efficient cooling and airflow equipment in operator planning. At the same time, the report's conclusion that new infrastructure is delayed rather than avoided supports continued multi-year demand for cooling equipment in new builds, provided developers adopt the staged, modular construction approach Majumdar recommends. The emphasis on workload-level energy measurement and verifiable load reduction could shift procurement criteria toward equipment with demonstrable efficiency and controllability at part-load and during curtailment events. Assessment (inference): ebm-papst should expect customers to ask for documented efficiency performance and controllability data that can support demand-response commitments to utilities, and could treat workload-aware SLAs and utility verification standards as an emerging specification channel for its fans and cooling solutions. Assessment (inference): the absence of quantified headroom estimates means the near-term capacity benefit remains unproven, so ebm-papst should not plan on demand-side measures materially slowing new data center cooling orders before 2030.
原文全文
Data Centers Can Delay, Not Dodge, the Power Crunch
Efficiency gains and flexible workloads may create near-term capacity for AI, but utilities will need proof that those reductions can be delivered when the grid needs them.
Data center operators facing power constraints can accommodate more AI computing by improving efficiency and shifting flexible workloads, but those measures are unlikely to remove the need for new electricity infrastructure.
That is the central conclusion of a new Infosys analysis of AI energy demand through 2030. The report argues demand-side measures can deliver usable capacity sooner than new generation, transmission, and grid upgrades. However, it also points to a harder question for developers, utilities, and customers alike: how much of that flexibility is actually available when the grid needs it most?
Mit Majumdar, executive vice president and global head of services, utilities, resources, and energy at Infosys, told Data Center Knowledge that AI-driven energy management, advanced cooling, and peak-load optimization can create meaningful near-term headroom. He did not provide a numerical estimate of additional AI capacity those measures could support.
“However, [these measures] are more likely to delay rather than eliminate the need for new infrastructure,” Majumdar said. “The best path forward is a dual-track strategy: maximize existing capacity while accelerating investment in generation, transmission, and grid modernization.”
Match Power Flexibility to the Right Workloads
The Infosys analysis identifies a mismatch between AI adoption cycles measured in months and energy infrastructure development measured in years. Operators can respond in part by changing when computing occurs, but the amount of flexibility depends on the workload.
“Flexible workloads such as model training, retraining, and batch processing can often be scheduled around grid conditions, while real-time inference and customer-facing applications generally cannot,” Majumdar said.
A facility serving both categories, therefore, cannot assume that its entire AI load is available for curtailment. Operators need to distinguish between work that can wait and applications whose customers require an immediate response.
Customer agreements must also reflect that distinction. Majumdar said broader flexibility will require service-level agreements (SLAs) that match workload requirements, along with demand-response incentives and pricing structures that reward customers for shifting non-urgent computing.
“Greater flexibility will require new commercial models, including workload-aware SLAs, demand-response incentives, and pricing structures that reward customers for shifting non-urgent compute,” he said.
The commercial question extends beyond whether a task can technically run later. Operators need customer commitments that make scheduling changes available when grid conditions require them.
Phase Capacity Around Changing Demand
Efficiency improvements also create uncertainty for developers deciding how much infrastructure to build. AI adoption is increasing computing demand, even as advances in models, chips, and cooling continue to change the power required to deliver that compute.
The report recommends choosing models suited to the task and applying techniques such as quantization, pruning, and knowledge distillation to reduce computational requirements. It also calls for measuring energy use and carbon emissions at the workload level.
Majumdar said developers should respond with staged construction rather than locking in every phase of a project to current assumptions.
“A modular approach allows capacity to scale as demand evolves while preserving flexibility to benefit from advances in AI models, chips, and cooling technologies,” he explained.
That approach gives developers opportunities to adjust later phases as customer requirements and equipment capabilities become clearer. It also keeps efficiency gains in the planning process rather than treating demand growth as the only variable.
“The goal is to avoid both overbuilding and underestimating long-term demand,” Majumdar said.
Prove Load Reductions Before Relying on Them
For utilities considering demand-side savings as support for new data center connections, projections alone are not enough. They need to determine whether operators can deliver reductions under the conditions that matter to grid reliability.
“Utilities should require measurable and verifiable proof, including historical performance, real-time monitoring, and contractual commitments to reduce load when needed,” Majumdar said.
Historical performance can support a claim, while real-time monitoring and enforceable commitments establish how that claim will be tested in operation. Operators and utilities also need to agree in advance on responsibility if the promised flexibility fails to materialize.
Majumdar argued neither party should bear the entire burden.
“Risk should be shared: operators should stand behind performance claims through guarantees, while utilities should establish clear qualification and verification standards to ensure reliability,” he said.