US data center land spend hits ~$6B in H1 2026, up 79%, as power access drives pricing
Intelligence brief
What happened US purchases of land for future data centers reached roughly $6 billion in the first half of 2026, up 79% year over year, according to Avison Young, as reported by Data Center Knowledge on 14 October 2026 and drawn from the firm's Q2 2026 Data Center Market report. The spending reflects competition among hyperscalers, neocloud providers, energy-first developers and investors to secure sites for large AI campuses. Avison Young's John Andril, manager of market intelligence, told TechTarget that "the biggest thing right now is speed to power." In Northern Virginia, entitled land without power can sell for roughly $4 million an acre versus at least $6 million an acre for powered land, though entitlements, infrastructure and other site characteristics also affect prices, so the comparison does not isolate the value of electricity alone. Industry analyst Neil Osnato said the premium is "increasingly payment for uncertainty removed, not just for megawatts nearby." An Altus Group analysis of 80 verified data center land transactions in August found committed utility load was the strongest predictor of land pricing. The report also details a Plug Power–Stream Data Centers transaction in Graham, Texas, and Loudoun County records showing SDC Twin Creeks Parent LLC paid $615.05 million for 97.15 acres in November 2025. ### Key figures - US data center land spending: about $6 billion in H1 2026, up 79% year over year (Avison Young). - Northern Virginia land pricing: roughly $4 million per acre for entitled land without power; at least $6 million per acre for powered land. - Altus Group analysis (80 verified transactions, August): sites tied to 230-kV or 500-kV infrastructure traded at roughly 2.4x the pricing of sites tied to 138-kV or lower infrastructure. - Power-ready definition: electrical infrastructure deliverable within about 18 months, roughly matching building preparation time for initial load. - Campus planning rule of thumb: about 0.5 to 1 acre per megawatt, with higher densities possible in land-constrained markets. - Plug Power–Stream Data Centers: $50 million base price plus up to $26.5 million in additional consideration tied to electrical load ultimately established, using a 164-MW reference capacity; Plug deposited $6.5 million with Oncor for a requested 164 MW and posted a $7.75 million letter of credit under the ERCOT Batch Zero agreement; project includes about 66 acres, development rights and grid-interconnection assets. The deal was later restructured: Stream acquired high-voltage electrical infrastructure for $40 million in August, with land and remaining interconnection assets subject to closing conditions. - Loudoun County: SDC Twin Creeks Parent LLC paid $615.05 million for 97.15 acres in November 2025, about $6.33 million per acre; Dominion Energy separately paid $45 million for about 14 acres. - Lower-cost markets: land worth roughly $10,000 an acre without a viable power path can reach six figures per acre after infrastructure and utility relationships are established. ### Why it matters to ebm-papst This is a demand-side signal rather than a direct competitive threat. Land spending at this scale implies a pipeline of large AI campuses whose economics hinge on speed to power, which in turn shapes cooling architecture choices — high-density liquid cooling, rear-door heat exchangers, and air-side economization all require different fan and blower content per megawatt. The 0.5–1 acre per megawatt planning rule and the 18-month power-readiness benchmark give a rough timing frame for when equipment specifications are likely to be locked in. Assessment (inference): ebm-papst's opportunity is greatest where power-constrained sites force higher rack densities and more aggressive thermal management, since those configurations typically increase fan and blower content and raise the value of high-efficiency, controllable air movement. Assessment (inference): the shift toward power-first site selection also favors suppliers that can engage early with developers and utilities on load-forecast and cooling-design assumptions, rather than bidding late on commodity fan packages. Assessment (inference): the Plug Power–Stream structure, where consideration was tied to capacity actually established, suggests developers are pricing power uncertainty explicitly; suppliers exposed to delayed projects should expect similar conditionality in their own order pipelines. Assessment (inference): the Loudoun County pricing and the Texas restructuring indicate continued capital concentration in a few competitive markets, so ebm-papst should track interconnection-queue and substation timelines as leading indicators of order timing rather than land transactions alone.
Full text
AI Data Center Land Buying Hits $6B as Power Premiums Rise
US data center land spending hit roughly $6 billion in the first half of 2026, as power access now drives land value and pricing more than location alone.
US purchases of land for future data centers reached about $6 billion in the first half of 2026, up 79% from a year earlier, according to Avison Young.
The spending reflects demand for large AI campuses, as hyperscalers, neocloud providers, energy-first developers and investors compete to secure sites for new computing capacity, according to the Q2 2026 Data Center Market report.
For data center operators, the stakes are both operational and financial. Delayed power can push back capacity delivery, complicate customer commitments and leave expensive buildings waiting to enter service.
“The biggest thing right now is speed to power,” John Andril, manager of market intelligence at Avison Young, told TechTarget in an interview.
In Northern Virginia, entitled land without power can sell for roughly $4 million an acre, compared with at least $6 million an acre for powered land, Andril said. Entitlements, infrastructure and other site characteristics also affect prices, so the comparison does not isolate the value of electricity alone.
“The premium is increasingly payment for uncertainty removed, not just for megawatts nearby,” said Neil Osnato, an industry analyst who has examined data center land transactions.
Committed Power Drives Land Value
An Altus Group analysis of 80 verified data center land transactions in August found committed utility load was the strongest predictor of land pricing.
Sites associated with 230-kilovolt or 500-kV infrastructure traded at roughly 2.4 times the pricing of sites associated with 138-kV or lower infrastructure, according to the analysis.
Transmission access can reduce the upgrades required to serve a project. In some cases, existing infrastructure can also shorten the regulatory process and save about a year, Andril said. However, proximity to a transmission line doesn’t guarantee that a utility can deliver the required capacity on schedule.
“If you don’t have power until the early to mid-2030s, you’re probably not going to get a lot of interest,” Andril said.
Andril said a genuinely power-ready property generally needs electrical infrastructure deliverable within about 18 months, roughly matching the time needed to prepare a building for its initial load. Developers also need clarity on the equipment required for a substation and who will fund and build it.
For campus planning, developers generally use about 0.5 to 1 acre per megawatt as a rule of thumb, Andril said, although land-constrained markets can support higher densities. A large project, therefore, requires both enough land and a credible plan for delivering its electricity.
A Texas Deal Puts a Value on Power
A transaction involving Plug Power and Stream Data Centers illustrates how power capacity can affect a project’s economics.
Plug agreed to sell its Graham, Texas, project to Stream for $50 million, with up to $26.5 million in additional consideration tied to the electrical load capacity ultimately established for the project. The agreement used a 164-megawatt (MW) reference capacity.
Plug had an interconnection request with Oncor and had deposited $6.5 million with the utility to secure a requested 164 MW of load. It also posted a $7.75 million letter of credit under the ERCOT Batch Zero agreement. The project includes about 66 acres, development rights and grid-interconnection assets.
The transaction was later restructured. Stream acquired high-voltage electrical infrastructure for $40 million in August, while the land and remaining interconnection assets remained subject to closing conditions.
The original agreement shouldn’t be described as a completed $76.5 million land sale. Its significance is that additional consideration depended on the capacity ultimately established, putting a price on the uncertainty surrounding the project’s power supply.
Northern Virginia Shows the Stakes
Loudoun County records show SDC Twin Creeks Parent LLC, a data center developer, paid $615.05 million for 97.15 acres in November 2025, or about $6.33 million an acre.
The property is part of the Twin Creeks data center development in Leesburg, Va. Dominion Energy separately paid $45 million for about 14 acres associated with the development.
The transactions don’t isolate electricity’s contribution to the land prices. Entitlements, development rights, site assembly and market conditions also influence valuations. They illustrate the scale of investment in data center sites in one of the country’s most competitive markets.
Andril said the effect can be pronounced in lower-cost markets, too. Land that might sell for roughly $10,000 an acre without a viable data center power path can become worth six figures per acre after developers establish the infrastructure and utility relationships needed for a large project.
Utilities Want Proof Developers Are Serious
Utilities face a planning problem of their own. They must prepare for large new loads without spending billions of dollars on projects that never materialize. Developers, meanwhile, want confidence in power delivery before committing substantial capital to a site.
Andril described the problem as a “chicken-and-egg” situation.
Letters of credit, take-or-pay agreements and stricter interconnection-queue requirements can help utilities separate serious projects from speculative requests. Andril said established developers and end users can support those measures because removing speculative projects makes legitimate demand easier to evaluate.
Onsite generation offers another option. Developers can use it to support initial operations while waiting for utility infrastructure, Andril said. Whether that approach makes financial sense depends on generation costs and the project’s economics.
For data center operators, those factors belong in site selection and project underwriting from the start. A land deal can look attractive on price and location, yet fail to meet the business case if the power needed to serve customers arrives too late.