# TRG ranks Virginia top US state for AI data center readiness with score 100; Ohio second at 88.2

- Source: Data Center Knowledge (T2)
- Published: 2026-10-12
- Score: 23.8
- Tags: Market data, Datacenter
- Original: https://www.datacenterknowledge.com/data-center-site-selection/virginia-tops-ai-data-center-readiness-ranking-as-smaller-markets-advance

## Intelligence brief

### What happened TRG DataCenters published a US state-level AI data center readiness ranking in August 2026, reported by Data Center Knowledge on 2026-10-12. The study compares 24 states using mapped large-scale AI data center sites, power capacity, electricity use, estimated annual carbon emissions, and the share of mapped facilities located in areas of high water stress. Virginia placed first with a readiness score of 100, ahead of Ohio (88.2), Tennessee (83.7), Georgia (81.8), Texas (80.8) and South Carolina (80.5). TRG CEO Chris Hinkle told Data Center Knowledge that the balance between scale and resource efficiency matters as much as raw megawatts when planning long-term infrastructure. TRG cautions that capacity figures reflect only the AI infrastructure in its dataset, not each state's total data center market, and that its water-stress measure describes facility locations rather than actual water consumption or the impact of individual cooling systems. ### Key figures - Virginia readiness score: 100; Ohio 88.2; Tennessee 83.7; Georgia 81.8; Texas 80.8; South Carolina 80.5 - Virginia: seven mapped large AI sites, 1,085 MW - Ohio: 1,410 MW mapped capacity (about 30% more than Virginia) - Tennessee: 1,373 MW mapped capacity - Texas: 13 large AI sites, 1,301 MW combined; 58.8% in areas of high water stress - South Carolina: one large AI site, 142 MW - Mississippi: more than 500 MW of AI capacity already supported - Estimated annual CO2 emissions: about 2.3 million tons for Virginia's mapped AI facilities, roughly 4.5 million tons in Ohio and 4.3 million tons in Tennessee - Grid carbon intensity serving Virginia's mapped facilities: roughly one-third lower than Ohio's - Share of mapped data centers in high water-stress areas: about one-third in Virginia, none in Ohio, 7% in Tennessee - Study scope: 24 states; publication date August 2026 ### Why it matters to ebm-papst This ranking is a demand-signal map rather than a procurement decision, but it points to where AI data center cooling and air-movement demand is likely to concentrate and how it will be constrained. Virginia, Ohio, Tennessee, Georgia and Texas remain the largest mapped AI capacity clusters, which supports continued OEM and aftermarket opportunities for precision cooling fans, air handling and motorized impellers in those states. At the same time, the water-stress findings are a direct technical signal: Texas has 58.8% of mapped facilities in high water-stress areas, and about one-third of Virginia's mapped sites face similar conditions. Hinkle explicitly expects this to push developers toward closed-loop or air-based cooling, recycled water and better siting. Assessment (inference): air-based and closed-loop cooling architectures typically require more air movement per unit of heat rejected than water-cooled designs, which could raise fan content per site and shift the mix toward higher-efficiency, higher-static-pressure EC fan solutions where ebm-papst competes. Assessment (inference): the emergence of smaller markets such as South Carolina, Mississippi, Iowa and New York on the strength of low-carbon power and low water stress suggests a more geographically fragmented pipeline, which would favor suppliers with local application engineering and service coverage rather than single-hub logistics. Assessment (inference): TRG's caveat that statewide electricity advantages do not guarantee site-level power availability implies that grid connection and transmission constraints, not just state rankings, will gate project timing; ebm-papst should treat announced capacity as a leading indicator with uncertain conversion rather than committed volume. No specific figures on fan or cooling equipment demand were disclosed in the source.

## Full text (original)

- Data Center Site Selection
- Data Center Construction
- Energy & Power Supply
- Sustainability
- Industry Trends
Virginia Tops AI Data Center Readiness Ranking as Smaller Markets Advance
TRG DataCenters’ August 2026 ranking places Virginia in the lead, while states with abundant power, low-carbon electricity, and favorable water conditions gain ground.
Power supply and water availability could help states outside established data center hubs compete for AI infrastructure investment, according to a new survey of US states from TRG DataCenters. The report, published in August 2026, compares 24 states using measures of infrastructure scale and environmental exposure and points to a more geographically diverse market as AI demand expands.
Virginia topped the August ranking of states positioned for AI data center growth, but the findings also suggest smaller markets can compete by offering a favorable combination of electricity supply, lower-carbon generation, and water availability.
“When planning infrastructure for the long term, that balance between scale and resource efficiency matters as much as raw megawatts,” Chris Hinkle, CEO of TRG DataCenters, told Data Center Knowledge.
TRG’s analysis considered mapped large-scale AI data center sites, power capacity, electricity use, estimated annual carbon emissions, and the proportion of mapped facilities in areas of high water stress. Capacity figures reflect the AI infrastructure included in TRG’s dataset and do not represent each state’s total data center market.
Virginia’s Lead Comes with Water Constraints
Virginia received a readiness score of 100, followed by Ohio at 88.2, Tennessee at 83.7, Georgia at 81.8, and Texas at 80.8. TRG’s dataset mapped seven large AI sites in Virginia totaling 1,085 MW of capacity, while Ohio and Tennessee showed higher mapped capacities – 1,410 MW in Ohio and 1,373 MW in Tennessee. Virginia’s advantage reflects performance across several measures, including lower estimated grid carbon intensity serving the mapped facilities.
Hinkle said Ohio’s mapped AI capacity was around 30% greater, but the grid serving Virginia’s facilities had roughly one-third lower carbon intensity than Ohio’s. “As a result, the AI facilities in our dataset are associated with around 2.3 million tons of CO2 emissions annually, compared with roughly 4.5 million tons in Ohio and 4.3 million in Tennessee,” he said.
Water – or lack thereof – is a complicating factor. About one-third of Virginia’s mapped data centers are located in areas of high water stress, compared with none in Ohio and just 7% in Tennessee. “One factor Virginia will need to continue managing as the market expands is site selection around water availability,” Hinkle said. Those differences make the ranking a starting point for evaluating markets rather than evidence that development conditions are uniform within a state.
Smaller Markets Offer Competing Advantages
South Carolina placed sixth with a score of 80.5, just behind Texas, despite having only one large AI site and 142 MW of capacity in the study. “What surprised us most was South Carolina,” Hinkle said. “It has just one large AI data center site and around 142 MW of capacity, yet it finished almost level with Texas in our overall readiness ranking, despite Texas having 13 large sites.” He attributed that performance partly to the state’s nuclear-heavy electricity supply and the absence of mapped facilities in areas of high water stress.
Hinkle also pointed to New York, Iowa, and Mississippi. New York combined relatively limited large-scale AI capacity with one of the lowest-carbon grids in the dataset, while Mississippi already supported more than 500 MW of AI capacity. “States that can combine reliable power with a relatively low-carbon electricity mix and favorable water conditions could become increasingly attractive as demand expands,” he said.
Texas Faces a Siting Challenge
Texas had the largest number of AI sites in the study – 13, with a combined capacity of 1,301 MW. However, 58.8% of those facilities were located in areas of high water stress. Hinkle said he expects those conditions to influence cooling choices and project locations. “That is likely to encourage more sophisticated siting and infrastructure strategies rather than simply slowing development,” he said. “We could see greater use of approaches such as closed-loop or air-based cooling, recycled water, and locations where local water conditions are more favorable.”
TRG notes that the water-stress measure describes facility locations and does not establish actual water consumption or the impact of individual cooling systems. Developers still need to assess those conditions at the project level.
From Readiness to Deliverable Infrastructure
Statewide advantages must also translate into infrastructure that developers can use. A relatively small share of statewide electricity use does not, by itself, establish that a particular site has power available for expansion.
“Grid connections, transmission capacity, fiber connectivity, build-ready sites, and long-term power availability can all influence where major projects ultimately land,” Hinkle said. For emerging markets, those requirements determine whether attractive resource conditions can support projects at scale. For established hubs, the requirements shape where additional development can proceed.
“The result could be a more geographically diverse AI infrastructure market as developers match projects with the locations best equipped to support them.”