# Liaoning picks 22 first-batch '15th Five-Year' storage projects totaling 3.15GW, with hyperstrong, CATL, Sungrow selected

- Source: News · Sungrow (T2)
- Published: 2026-10-11
- Score: 51.4
- Tags: Market data, ESS
- Companies: Sungrow (300274.SZ), CATL, hyperstrong
- Original: https://m.sohu.com/a/1086246969_122014422?scm=10001.325_13-325_13.0.0-0-0-0-0.5_1334

## Intelligence brief

### What happened On 10 October, the Liaoning Provincial Development and Reform Commission published a public notice ("Public Notice on the Selection Results of the First Batch of New-Type Energy Storage Projects under the 15th Five-Year Plan") listing 22 selected projects with a combined scale of 3.15GW. The notice was reported by the industry outlet Energy Storage and Electricity Market. The largest single project on the list is Anhui Qingfeng Energy's Gaizhou 350MW/2800MWh compressed-air energy storage (CAES) project, implying an 8-hour storage duration. Two further large projects use all-vanadium flow battery technology: Beijing Kegong Information's Shenbei New District 200MW/800MWh all-vanadium flow battery storage station, and Shenyang Chengtou Group's Sujiatun District 200MW/800MWh independent storage project combining vanadium flow and lithium iron phosphate (LFP) batteries. According to the report, the inclusion of these three projects reflects the selection guidance of favouring peak-shaving-type stations and prioritising long-duration, intrinsically safe technologies such as compressed air and all-vanadium flow batteries. On the owner side, hyperstrong secured two projects, both as a standalone entity and as a shareholder: the Anshan High-Tech Zone new-type energy storage project (200MW) and the Guojian Century Energy Operation Management (Liaoyang) Zhangtai 200MW/800MWh independent storage project. Equipment manufacturers CATL, Sungrow, Envision Energy and Wanbang New Energy, as well as central state-owned energy players China Resources and Guohé Investment, were also selected. The report notes a striking share of cross-sector players, including Chenfeng Technology (electronic components), Nanwei Software (software), Tieling Carbon Cycle Biotechnology and Dalian Changlin Management Consulting, which the outlet reads as a sign of Liaoning's relatively open storage market. Selection is only the starting point: consumption/absorption conditions, financing and engineering execution still have to be resolved before projects are commissioned. ### Key figures - 22 projects selected in Liaoning's first batch of 15th Five-Year new-type energy storage projects - Total scale: 3.15GW - Largest single project: Anhui Qingfeng Energy, Gaizhou, 350MW/2800MWh compressed-air storage, 8-hour duration - Beijing Kegong Information, Shenbei New District: 200MW/800MWh all-vanadium flow battery - Shenyang Chengtou Group, Sujiatun District: 200MW/800MWh vanadium flow + LFP hybrid independent storage - hyperstrong: two projects, including Anshan High-Tech Zone 200MW and Zhangtai (Liaoyang) 200MW/800MWh - Notice publication date: 10 October (year not stated in the source; the item is dated 2026-10-11) - No pricing, investment value, capacity-share or commissioning-timeline figures were disclosed. ### Why it matters to ebm-papst Liaoning's first 15th Five-Year storage batch is a demand signal for air-moving and thermal-management components inside stationary storage systems. Compressed-air storage (350MW/2800MWh) and vanadium-flow plus LFP hybrid projects (200MW/800MWh each) require large-scale cooling, ventilation and air handling, and the two 200MW/800MWh projects alone represent substantial containerised or building-based thermal equipment content. The presence of CATL, Sungrow, Envision Energy and hyperstrong as selected owners/investors matters because these are exactly the system integrators and OEMs that specify fans and blowers for battery containers, PCS cabinets and HVAC skids; being designed into their Liaoning projects can translate into repeat orders across their national pipelines. Assessment (inference): The explicit preference for long-duration and intrinsically safe technologies (compressed air, vanadium flow) may shift component demand away from conventional LFP container cooling toward larger air-handling and process-cooling architectures, where ebm-papst's high-efficiency axial and centrifugal fans could compete, though this is a technology-mix judgement rather than a stated procurement plan. Assessment (inference): The unusually high share of cross-sector entrants (software, electronics, consulting) suggests a fragmented owner base with limited in-house engineering, which typically increases reliance on integrators and component suppliers for design support — a potential channel opportunity. Assessment (inference): Because selection is only a first step and absorption, financing and construction remain unresolved, near-term order conversion is uncertain and should not be treated as committed volume.

## Full text (English translation)

Liaoning's first batch of '15th Five-Year' energy storage projects: 3.15GW, with hyperstrong/CATL/Sungrow/Envision/China Resources and others selected

(Source: Energy Storage and Electricity Market)

Energy Storage and Electricity Market has learned that on 10 October, the Liaoning Provincial Development and Reform Commission issued the "Public Notice on the Selection Results of the First Batch of New-Type Energy Storage Projects under the 15th Five-Year Plan", covering a total of 22 projects with a combined scale of 3.15GW.

Among them, Anhui Qingfeng Energy's Gaizhou 350MW/2800MWh compressed-air energy storage project is the largest single project on this list, equivalent to an 8-hour storage duration. There are also two large-scale projects using all-vanadium flow battery storage technology: Beijing Kegong Information Company's Shenbei New District 200MW/800MWh all-vanadium flow battery energy storage station project; and Shenyang Chengtou Group's Sujiatun District 200MW/800MWh vanadium flow + lithium iron phosphate hybrid battery independent energy storage project. The selection of these three projects also reflects the guiding approach at the project selection stage of "focusing on peak-shaving-type stations" and "giving priority to supporting the application of long-duration energy storage technologies with intrinsic safety characteristics, such as compressed air and all-vanadium flow".

Looking at the project owners, hyperstrong won two projects both as an independent entity and as a shareholder, namely: the Anshan High-Tech Zone new-type energy storage project (200MW), and Guojian Century Energy Operation Management (Liaoyang) Co., Ltd.'s Zhangtai 200MW/800MWh independent energy storage project; equipment manufacturers such as CATL, Sungrow, Envision Energy and Wanbang New Energy, as well as central state-owned energy enterprises such as China Resources and Guohé Investment, were all successfully selected.

It is worth noting that cross-sector players account for a prominent share of this list, with Chenfeng Technology (electronic components), Nanwei Software (software), Tieling Carbon Cycle Biotechnology, and Dalian Changlin Management Consulting (a consulting company) among those selected, reflecting the relatively high degree of openness of the Liaoning energy storage market. Passing the selection is only the starting point for the projects; subsequently, substantive issues such as consumption conditions, funding arrangements and engineering implementation will need to be resolved to push the projects into operation.

## Full text (original)

辽宁“十五五”第一批储能项目：3.15GW，海博思创/宁德时代/阳光电源/远景/华润等入选
（来源：储能与电力市场）
「储能与电力市场」获悉，10月10日，辽宁省发改委发布《关于“十五五”第一批新型储能项目遴选结果的公示》，共计22个项目，总规模3.15GW。
其中，安徽清峰能源盖州市350MW/2800MWh压缩空气储能项目，是本次清单里单体规模最大项目，折算储能时长8h。另外还有两个大规模的采用全钒液流电池储能技术的项目：北京市科工信息公司的沈北新区200MW/800MWh全钒液流电池储能电站项目；沈阳城投集团苏家屯区200MW/800MWh全钒液流+磷酸铁锂混合电池独立储能项目。这三个项目的入选，也体现了项目遴选阶段“以调峰型电站为主”、“优先支持压缩空气、全钒液流等长时且具备本质安全特性的储能技术应用”的指导思路。
从项目业主来看，海博思创同时以独立主体和参股股东的身份斩获两个项目，分别是：鞍山市高新区新型储能项目（200MW）、国建世纪能源运营管理（辽阳）有限公司张台200MW/800MWh独立储能项目；宁德时代、阳光电源、远景能源、万帮新能源等设备厂商，华润、国核投资等能源央企均成功入选。
值得注意的是，这份名单跨界玩家占比突出，晨丰科技（电子元件）、南威软件（软件）、铁岭碳循环生物科技、大连长霖管理咨询（咨询公司）企业等入围，体现辽宁储能市场较高的对外开放度。遴选通过仅为项目起步，后续将解决消纳条件、资金落实、工程落地等实质问题，推动项目投运。